Page 209 - Pipelines and Risers
P. 209

182                                                              Chapter 12


           General Principle
           Pipelay  semisubmersibles are effectively a  floating  factory  which  weld  line  pipe  joints
           together and installs the pipe accurately on the seabed. Pipelay barges used originally in the
           Gulf  of  Mexico experienced difficulty in  the  North  Sea  in  laying  pipelines  quickly and
           without  damage.  Consequently, pipelay  semisubmersibles were  developed. These  vessels
           perform the pipelaying in the following sequence (see Figure 12.2).


              Handle 12 m pipe joints onto deck, using vessel cranes;
              Handle joints onto conveyors for beveling and joining joints into pairs (double joints);
              Storing double joints;
              Join double joints onto main firing line;
              Lay pipeline onto seabed without overstressing the line.


           To perform these tasks the vessel should exhibit the following capabilities:

              Stable platform and constant tension tensioners to pennit the line to be “S laid into the
              sea (see Figure 12.3). Should the vessel move too much (i.e. due to weather) the pipeline
              may overstress and possibly buckle.
              Method of handling joints quickIy. These vessels can install up to 5km of pipeline a day
              (one joint every 3.5 minutes);
              Method of  welding and nondestructive testing of joints with  sufficient speed to average
              3.5 minutes per joint. The time given to weld a joint is assisted by the double joints, and
              having up to 4 welding stations on the firing line.

           This means that each weld can actually take (3.5 x 4 x 2) 28 minutes to complete.


           Installation CapabititiedConstraints
           Pipelay semisubmersibles can  install  in  a wide range of  diameter pipelines (6” to 40”) in
           water depths from 10 to 1500m deep, the deepest to date is 600m.

           The main constraints of the pipelay vessels is the cost, they typically require 400 personnel,
           two anchor handling vessels, a survey vessel and the supply vessels for transporting linepipe.
           The total cost of the spread varies annually depending  on the equipment rates etc.

           12.2.2  Pipelay Ships and Barges
           General Principle
           Pipelay ships install  pipelines  in  the  same manner  as  the pipelay  semisubmersibles. The
           principal difference is that these vessels are monohulls, and hence do not have as good sea
           keeping abilities as the semisubmersibles. Flat barges have worse sea keeping abilities than
           the ships and are used only in the calmer wave climates.
   204   205   206   207   208   209   210   211   212   213   214