Page 211 - Pipelines and Risers
P. 211

184                                                              Chapter 12


           A major consideration in pipeline reeling is that the plastic deformation of the pipe must be
           kept within limits specified by  the relevant codes. The existing reelship reflects such code
           requirements.


           Installation CapabilitiedConstraints
           Due  to  the  requirement  to  reel  the  pipeline  onto  a  small  diameter  drum, the  pipeline
           experiences some plastic strain. The permissible amount of strain (and ovalisation of the pipe)
           limits the maximum diameter of the pipeline that can be installed using this method. Usually,
           depending on the wall thickness, the maximum diameter is 16-inch. Also, due to the limited
           size of  drum, only short lengths of  pipe can  be  laid (usually 3-15 km depending on  pipe
           diameter). However, it is possible to install larger lines if more drums of pipe are available.


           Accepting the constraints of this method, the reel method of installation has been proven to be
           a reliable and economical method of installing pipelines. The main advantages of the system
           are:

              Short offshore installation duration;
              Minimum offshore spread (no anchor handlers).

           12.2.4  Tow or Pull Vessels
           This method is applied to short lines, usually less than  4 km, (7 km has been laid), which
           would prove difficult, impossible, or more expensive to install from a pipelay vessel.


           General Principle
           The pipeline is fabricated onshore, and towed into the sea when  it is completed (see Figure
           12.4). The buoyancy of the line is selected and designed to verify that  a controlled depth tow
           can be performed. Usually two rigs tow the pipeline to location; one leading and one trailing.
           On location the pipeline is positioned and flooded.

           This method of installation is usually used when several flowlines are fabricated together (i.e.
           a bundle).

           Installation CapabilitidConstraints
           The main advantages of fabricating a pipeline onshore are:

              Low equipment costs compared to fabricating offshore;
              Long fabrication duration's permitting more difficult fabrication techniques to be applied.
              Some fabrication techniques, such as using bundling (several pipelines tied together and
              sometimes installed into a carrier pipe), cannot be performed by offshore vessels.
              Pipeline fabrication is not prone to weather interruptions.

           However, the constraints of using the tow/pull methods are:
   206   207   208   209   210   211   212   213   214   215   216