Page 175 - Practical Power System and Protective Relays Commissioning
P. 175

Power System Fault Analysis Chapter | 16  175


             constructed, starting from an infinite source and leading to the fault posi-
             tion. All values of impedance used to construct the network must refer to
             the same MVA base. For consistency, always use the percent impedance to
             a base of 100 MVA.
                If the fault being considered is a three-phase fault, then there will only be
             positive-sequence quantities present, therefore only positive-sequence impe-
             dances need to be considered.
                The impedance to the fault can now be calculated, and from this the fault
             current can then be calculated (I F ). The fault current in other parts of the net-
             work can be derived using network analysis techniques, with the fault current
             at the relay point.
                If the protection relay is an impedance measuring type (i.e., distance pro-
             tection) then it may only be necessary to calculate the impedance to the
             fault.
                Example 1:
                Three-phase balanced fault (Fig. 16.17)
                Calculations:
                Total impedance 5 Z 5 0.4 1 1.5 1 8.3 5 10.2
                MVAF 5 10,000/Z% 5 10,000/10.2 5 980 MVA
                I F 5 MVAF/(kV 3 1.732) 5 980/(132 3 1.732) 5 4.286 kA
                Example 2:
                Single phase-to-earth fault (Fig. 16.18)


























             FIGURE 16.17 Three-phase balanced fault.
   170   171   172   173   174   175   176   177   178   179   180