Page 373 - Practical Power System and Protective Relays Commissioning
P. 373

Chapter 23





             Substation Testing and


             Commissioning Time Schedules
             and Resources Management





             23.1 INTRODUCTION
             In order to complete the substation commissioning work in efficiently and
             effectively we should manage the activities involved in these tests and man-
             age resources to match each activity with the correct number of people with
             the appropriate skills and also manage the time to do these activities wisely,
             as increased time spent inevitably leads to increased costs.



             23.2 PRACTICAL EXAMPLE OF EXECUTED SUBSTATIONS
             23.2.1 Gas Insulated System Substation

             The substation has the following data:
                500/220 kV substation
                3 bays—500 kV feeders 1 2 spare feeders
                12 bays—220 kV feeders 1 2 spare feeders
                3 bays—transformers 500/220 kV and 3 transformers 220/11 kV
                20 feeders—11 kV feeders
                Refer to the following schedule for activities, required manpower, and
             required time to completion.
                A 5 no. of feeder bays, B 5 no. of transformer bays, C 5 no. of 11 kV
             feeders.
                Note that some activities can be done in parallel (Table 23.1).
                A 5 3 1 2 1 12 1 2 5 19
                B 5 3 1 3 5 6
                C 5 11 kV feeders 5 20
                For a substation in this example (Table 23.2), where A, B, C, D, F, G, P,
             N, K, and M are the 10 different engineers assigned to do this job.
                Total required months 5 6 months




             Practical Power System and Protective Relays Commissioning.
             DOI: https://doi.org/10.1016/B978-0-12-816858-5.00023-X     369
             © 2019 Elsevier Inc. All rights reserved.
   368   369   370   371   372   373   374   375   376   377   378