Page 236 - Practical Ship Design
P. 236

198                                                             Chapter 7


























                       0.00               0.10              0.20              0.30
                                                           2
                                          P  =  (Cb)”3  . SA


                            Fig. 7.5. (1 + K) values for use with Grigson friction line.




              7.1.5 Corrections for differences in hull geometry

              All the C,, values so far obtained relate to a geosim of the basis ship and further
              corrections must be made for any departures from this geometry.
                Although the use of the basis ship data must presuppose that the Cb value and the
              LCB position of the new design differ to only a minor extent from the values of the
              basis ship, corrections should be made for the effect of these features if they differ.
                A correction for a difference in Cb can be made by using the ratio of the C, values
              given for the  two block  coefficient values  on  one of  the  graphs given  in  this
              section.
                There is less data available to assist in making a correction for a change in LCB
              position but Guldhammer and Harvald’s data and some of Moor’s data can be used
              - again in the form of a ratio.
                Corrections for a change in L/B and/or the LIT ratio  can be made using the
              Mumford indices given in 56.7.
   231   232   233   234   235   236   237   238   239   240   241