Page 157 - Practical Well Planning and Drilling Manual
P. 157

Section 2 revised 11/00/bc  1/17/01  12:04 PM  Page 133








                                                                                  2.1.5
                                             Preliminary Work For the Drilling Program  [      ]



                       2.1.4. Time Estimates

                           Any estimate will be improved with more detail. Spreadsheets are
                       invaluable because they allow a great amount of detail, which can then
                       be totaled, diced in many different ways, and easily updated.
                           The cost of a well is, of course, intimately related to the time it
                       takes. In making a time estimate, break down the overall work into
                       small chunks and give reasonable time estimates, based on local expe-
                       rience, for each chunk. As the work progresses, the spreadsheet can be
                       updated by substituting the estimated times for the actual times, which
                       will update the forecast.
                           The time estimates will vary depending on the purpose of the esti-
                       mate. When planning a well, an estimate should give forecasts for
                       logistics. In this case, the shortest possible time should be estimated for
                       each operation—it is much easier to allow things to slip than to pull
                       supply of equipment forward. For cost estimates, use a reasonable
                       “average” time, not the shortest possible. This will give a different over-
                       all estimate.
                           I have created a spreadsheet (planner.xls) that takes a start date,
                       start time, and times for individual operations, and produces a forecast
                       for getting things to the rig. This spreadsheet can be downloaded from
                       my web site at  http://www.drillers.com, or you can build your own.
                       Figure 2-1 is an example of this spreadsheet.

                       2.1.5. Cost Estimates


                           Well cost estimates are made at different stages in the planning
                       process. These will vary by the level of detail possible and therefore by
                       the level of accuracy. Following are cost estimates that will usually be
                       needed as the project progresses.
                           Budget estimate. The accuracy of a budget estimate is ±25%. The
                       level of information usually given will include approximate location and
                       water depth, approximate target location and TVD, desired total depth
                       TVD, and desired completion status. Other information may be includ-
                       ed. For this type of estimate the best way is to look at the costs of offset
                       wells and make simple adjustments for depths, rig day rates, etc. Since
                       little engineering work can be done at this stage, you are making an edu-
                       cated guess. The spreadsheet discussed below can be used by taking a
                       previous estimate and revising it for best guess times, rates, and depths.


                                                     133
   152   153   154   155   156   157   158   159   160   161   162