Page 161 - Practical Well Planning and Drilling Manual
P. 161

Section 2 revised 11/00/bc  1/17/01  12:04 PM  Page 137








                                             Preliminary Work For the Drilling Program  [      ]
                                                                                  2.1.5




                           12.25 in hole        at 2450 m        4.0 days
                           9 5/8 in casing                       2.0 days
                           8 1/2 in hole        at 2900 m        4.0 days
                           TD logging                            3.1 days
                           Testing                               20.0 days
                           7 in liner                            2.0 days
                           Abandon well                          3.0 days
                           Release rig                           1.0 days
                           Weather downtime 5%                   2.5 days
                           Rig downtime 5%                       2.5 days
                           TOTAL:                                55.6 days


                       WELL COST ESTIMATE(see attached for details) :

                           Rig Move:             $      910,565
                           Drill, Log, & Suspend:  $    4,155,266
                           Compl. & Test:        $    1,679,447
                           TOTAL Base Estimate:  $    6,745,278
                           Contingency:          $       851,099
                           GRAND TOTAL:          $    7,596,377

                           Daily Operational Cost:  $         79,063





                           Costs broken down by cost code. The next level of detail gives a
                       cost breakdown by code. Times and depths relevant to the estimate are
                       carried forward from the front sheet. Some totals are calculated by this
                       sheet (such as rig rate x days), and some of the figures come from the
                       next sheet in the workbook.
                           The sheet is set out in three sections: the left column shows a code
                       and description for each line, the middle set of columns are used to
                       enter time or depth-dependent rates, and the right set of columns
                       either multiplies time or depth-related costs by the relevant figure, or
                       takes input from the next sheet. Most departments that require cost
                       estimates will be happy with the summary and costs by code sheets and
                       will not need further levels of detail. (See Fig. 2-3.)




                                                     137