                      [      ]  Well Programming
                       2.1.5




                       Fig. 2-2  Summary Sheet Example
                                AFE Well Cost Estimate
                                By: Steve Devereux


                       BUDGET TITLE             Example Exploration Well

                           Notes                               1. Assumes well logged, tested,
                                                                 and abandoned.
                           DATE                 12-Apr-97      2. Mob/demob costs are
                                                                 assumed split between
                                                                 4 wells.
                                                               3. Site survey costs assume
                                                                 mob/demob split between
                                                                 2 wells.
                                                               4. This well is designed with a
                                                                 conventional casing scheme.

                       VALUE of this estimate    $   7,596,377
                       Dry hole cost of well     $   5,916,929    ($1,679,447 less than total)
                           Contingency included  $      851,099    (Equivalent to 11% of the
                                                               total estimate)
                       Accuracy of estimate     15%            Budget cost should be $8,735,833


                       1) SUMMARY
                           This well cost estimate covers the drilling, logging, testing, and abandonment of
                       the first maximum concession commitment well.

                       2) ESTIMATES

                           Well time estimate:
                           Rig move, jack-up, preload  at 50 m  2.0 days
                           Drive 30 in conductor   at 135 m    2.0 days
                           NU diverter                         1.0 days
                           Drill 26 in hole       at 1000 m    2.0 days
                           20 in surface casing                1.0 days
                           17.5 in hole           at 1700 m    2.0 days
                           13 3/8 in casing                    1.5 days


                                                     136