Page 158 - Practical Well Planning and Drilling Manual
P. 158

Section 2 revised 11/00/bc  1/17/01  12:04 PM  Page 134








                      [      ]  Well Programming
                       2.1.5



                       Fig. 2-1 Spreadsheet “planner.xls” Example
                       Operational Lookahead Planner—Maximum Well
                        Start  Start  Minimum    Description               Notes
                        Date   Time   Duration

                        6-Mar  06:00 AM  32.00  Drive conductor     Load out 13-3/8 in casing
                        7-Mar   14:00  18.00  N/U diverter, clean to shoe
                                             9-5/8 in casing ready to
                                             load
                        8-Mar   8:00   14.00  Pilot hole
                        8-Mar   22:00  18.00  Open hole
                        9-Mar   16:00  18.00    Run and cement 13.375 in
                                             casing
                        10-Mar  10:00  18.00  N/D diverter, N/U and test
                                             BOP
                        11-Mar  4:00   10.00  RIH, drill shoe, circ, FIT  Logging engineers to rig
                        11-Mar  14:00  24.00  Drill ahead to 975 m TVDSS,
                                             POH
                        12-Mar  14:00  20.00  Logs inc. w/trip
                        13-Mar  10:00  20.00  Run and cement 9.625 in
                                             casing, WOC
                        14-Mar  6:00    6.00  N/U and test BOP
                        14-Mar  12:00   8.00  MU new BHA, RIH, gyro
                                             inside DP
                        14-Mar  20:00   5.00  Drill out, condition mud, FIT
                        15-Mar  1:00   48.00  Drill ahead to TD
                        17-Mar  1:00  120.00  Run logs APP, including 2
                                             trips
                        22-Mar  1:00   28.00  Run and cement 7 in liner
                        23-Mar  5:00    6.00  Run 8-1/2 in bit to TOL
                        23-Mar  11:00  14.00  Run 6 in bit / 3-1/2 in DP;
                                             drill flapper valve; RIH to
                                             landing collar.
                        24-Mar  1:00   10.00  Run scrapers and PBR mill
                        24-Mar  11:00  12.00  Run USIT in 7 in and CBL in
                                             9-5/8 in
                        24-Mar  23:00   5.00  VSP
                        25-Mar  4:00   17.00  RIH PH6 tubing; clean/circ, rack
                                             back
                        25-Mar  21:00  16.00  Clean TOL, set tieback packer,
                                             pressure test well, POH
                        26-Mar  13:00   3.00  L/D excess pipe from derrick
                        26-Mar  16:00  24.00  Rig up for well testing
                        27-Mar  16:00        Start first well test