Section 2 revised 11/00/bc 1/17/01 12:04 PM Page 134
[ ] Well Programming
2.1.5
Fig. 2-1 Spreadsheet “planner.xls” Example
Operational Lookahead Planner—Maximum Well
Start Start Minimum Description Notes
Date Time Duration
6-Mar 06:00 AM 32.00 Drive conductor Load out 13-3/8 in casing
7-Mar 14:00 18.00 N/U diverter, clean to shoe
9-5/8 in casing ready to
load
8-Mar 8:00 14.00 Pilot hole
8-Mar 22:00 18.00 Open hole
9-Mar 16:00 18.00 Run and cement 13.375 in
casing
10-Mar 10:00 18.00 N/D diverter, N/U and test
BOP
11-Mar 4:00 10.00 RIH, drill shoe, circ, FIT Logging engineers to rig
11-Mar 14:00 24.00 Drill ahead to 975 m TVDSS,
POH
12-Mar 14:00 20.00 Logs inc. w/trip
13-Mar 10:00 20.00 Run and cement 9.625 in
casing, WOC
14-Mar 6:00 6.00 N/U and test BOP
14-Mar 12:00 8.00 MU new BHA, RIH, gyro
inside DP
14-Mar 20:00 5.00 Drill out, condition mud, FIT
15-Mar 1:00 48.00 Drill ahead to TD
17-Mar 1:00 120.00 Run logs APP, including 2
trips
22-Mar 1:00 28.00 Run and cement 7 in liner
23-Mar 5:00 6.00 Run 8-1/2 in bit to TOL
23-Mar 11:00 14.00 Run 6 in bit / 3-1/2 in DP;
drill flapper valve; RIH to
landing collar.
24-Mar 1:00 10.00 Run scrapers and PBR mill
24-Mar 11:00 12.00 Run USIT in 7 in and CBL in
9-5/8 in
24-Mar 23:00 5.00 VSP
25-Mar 4:00 17.00 RIH PH6 tubing; clean/circ, rack
back
25-Mar 21:00 16.00 Clean TOL, set tieback packer,
pressure test well, POH
26-Mar 13:00 3.00 L/D excess pipe from derrick
26-Mar 16:00 24.00 Rig up for well testing
27-Mar 16:00 Start first well test
134