Page 162 - Practical Well Planning and Drilling Manual
P. 162
Section 2 revised 11/00/bc 1/17/01 12:04 PM Page 138
[ ] Well Programming
2.1.5
Total 53.6 days 2,486,363 428,440 24,222 25,682 18,333 10,000 147,642 21,389 46,977 15,278 24,000 268 26,778 3,275,370
Compl/Test 20.0 days 2,900 m 900,000 160,000 12,000 10,160 100 10,000 1,092,260
Drill/Suspd 30.6 days 2,900 m 1,451,363 244,440 12,222 15,522 18,333 10,000 134,442 21,389 42,777 15,278 15,000 153 15,278 1,996,195
12-4-97
Date : Cost Estimate Rig Moves 3.0 days 135,000 24,000 13,200 4,200 9,000 15 1,500 186,915
Compl, Test 45,000 8,000 600 508 4,400 1,400 3,000 5 500
Drill/Suspd 47,500 8,000 400 508 600 2,000 4,400 700 1,400 500 3,000 5 500 69,513
Cost Rates Rig Move 45,000 8,000 4,400 1,400 3,000 5 500
Fig. 2-3 Costs by Code Sheet Example AFE Well Cost Estimate Well: Example Exploration Well Steve Devereux Description TIME DEPENDENT ($/day) Rig rate Vessels Additional (catering, etc.) Cement serv. & pers. Mud logging Conductor driving eq Dock fees & base overheads Rental tools Consultants on rig Anderdrift survey tool ROV mob; drill 26 in, set 20 in Water Fuel (rig and vessels) TOTAL
Reporter:
A/C no.
87415
87201
138 87230 87530 87524 87555 87665 87551 87554 87551 87506 87554 87554