Page 439 - Six Sigma Demystified
P. 439

f i n a l   e x a m      419


                          28.	 	The	earliest	start	time	for	step	2b2	is
                              A.	5	days.
                              b.	6	days.
                              c.	12	days.
                              d.	15	days.


                          29.	 	The	latest	start	time	for	step	2b2	is
                              A.	5	days.
                              b.	6	days.
                              c.	10	days.
                              d.	11	days.


                          30.	 	If	we	don’t	define	the	critical	path	for	a	process,
                              A.	we	can’t	reduce	defect	levels	effectively.
                              b.	we	may	reduce	cycle	times	of	noncritical	path	activities,	which	won’t	have	as
                                much	of	an	impact	on	total	cycle	time.
                              c.	we	may	reduce	cycle	times	of	noncritical	path	activities,	which	will	have	no
                                impact	on	total	cycle	time.
                              d.	All	the	above	are	true.


                          31.	 	The	advantage	of	a	probabilistic	approach	to	PERT	analysis	is	that
                              A.	it	properly	considers	that	processes	are	not	deterministic.
                              b.	it	assumes	that	there	is	variation	in	activity	times.
                              c.	it	could	provide	a	more	realistic	estimate	of	project	completion
                                times.
                              d.	All	the	above	are	true.


                          32.	 	If	the	optimistic,	pessimistic,	and	most	likely	times	for	step	1	of	a	process	are	2,	9,
                              and	5	days	and	for	step	2	are	4,	13,	and	8	days,	then	the	best	estimate	for	the

                              total	cycle	time	for	the	two	steps	is
                              A.	13	days.
                              b.	13.34	days.
                              c.	8	days.
                              d.	22	days.


                          33.	 	If	the	optimistic,	pessimistic,	and	most	likely	times	for	step	1	of	a	process
                              are	2,	9,	and	5,	and	for	step	2	are	4,	13,	and	8	days,	then	the	best	estimate
                              for	the	standard	deviation	of	the	total	cycle	time	for	the	two	steps	is
                              A.	3.6	days.
                              b.	2.67	days.
                              c.	1.9	days.
                              d.	1.5	days.
   434   435   436   437   438   439   440   441   442   443   444