11 - PROJECT RISK MANAGEMENT






                   11.4.1.2 Cost Management Plan


                      See Section 11.4.1.2 of the PMBOK  Guide.
                                                    ®

                   11.4.1.3 Schedule Management Plan

                      See Section 11.4.1.3 of the PMBOK  Guide.
                                                    ®
                   11.4.1.4 Risk Register


                      See Section 11.4.1.4 of the PMBOK  Guide.
                                                    ®

                   11.4.1.5 Enterprise Environmental Factors

                      See Section 11.4.1.5 of the PMBOK  Guide.
                                                    ®

                   11.4.1.6 Organizational Process Assets

                      See Section 11.4.1.6 of the PMBOK  Guide.
                                                    ®

                   11.4.2 Perform Quantitative Risk Analysis: Tools and Techniques


                                                                       ®
                      The tools and techniques in Section 11.4.2 of the PMBOK  Guide for performing quantitative risk analysis are
                   applicable to performing quantitative risk analysis for software projects with the following extensions to Data Gathering
                   and Representation Techniques (11.4.2.1) and Quantitative Risk Analysis and Modeling Techniques (11.4.2.2).

                   11.4.2.1 Data Gathering and Representation Techniques


                                                    ®
                      See Section 11.4.2.1 of the PMBOK  Guide.
                      In addition, quantitative ratings of risk exposure can be based on numeric values, as illustrated in Table 11-3.
                   The entries in Table 11-3 are the products of the corresponding values of probability and normalized impacts; this




                                          Table 11-3. A Typical Quantitative Risk Exposure Matrix

                                         Impact       25          50          75         100

                                        Probability
                                          0.25        6.25        12.5       18.75        25
                                          0.5         12.5        25         37.5         50
                                          0.75       18.75        37.5       56.25        75

                                          0.95       23.75        47.5       71.25        95



          204      ©2013 Project Management Institute. Software Extension to the PMBOK  Guide Fifth Edition
                                                                   ®