11 - PROJECT RISK MANAGEMENT
11.4.1.2 Cost Management Plan
See Section 11.4.1.2 of the PMBOK Guide.
®
11.4.1.3 Schedule Management Plan
See Section 11.4.1.3 of the PMBOK Guide.
®
11.4.1.4 Risk Register
See Section 11.4.1.4 of the PMBOK Guide.
®
11.4.1.5 Enterprise Environmental Factors
See Section 11.4.1.5 of the PMBOK Guide.
®
11.4.1.6 Organizational Process Assets
See Section 11.4.1.6 of the PMBOK Guide.
®
11.4.2 Perform Quantitative Risk Analysis: Tools and Techniques
®
The tools and techniques in Section 11.4.2 of the PMBOK Guide for performing quantitative risk analysis are
applicable to performing quantitative risk analysis for software projects with the following extensions to Data Gathering
and Representation Techniques (11.4.2.1) and Quantitative Risk Analysis and Modeling Techniques (11.4.2.2).
11.4.2.1 Data Gathering and Representation Techniques
®
See Section 11.4.2.1 of the PMBOK Guide.
In addition, quantitative ratings of risk exposure can be based on numeric values, as illustrated in Table 11-3.
The entries in Table 11-3 are the products of the corresponding values of probability and normalized impacts; this
Table 11-3. A Typical Quantitative Risk Exposure Matrix
Impact 25 50 75 100
Probability
0.25 6.25 12.5 18.75 25
0.5 12.5 25 37.5 50
0.75 18.75 37.5 56.25 75
0.95 23.75 47.5 71.25 95
204 ©2013 Project Management Institute. Software Extension to the PMBOK Guide Fifth Edition
®