MONITOR AND CONTINUALLY IMPROVE PERFORMANCE               201




                                          Waste Minimization Validation Worksheet

           Company name: ___________________________
           Location: ________________________________
           Date: ___________________________________
           Alternative description: _____________________
           Alternative tracking number: _________________
                                                           Estimated  Actual % Difference    Comments
           Project Duration
           Space Requirements

           Implementation Cost
             Machine costs
                Machine cost
                Site development
                Material costs
                Building modification costs
                Permitting and inspection costs
                Contractor fees
                Start up costs
                Initial training costs
             Operating expenses
                Utility cost impacts
                Input material changes
                Labor cost impacts
                Supervision cost impacts
                Maintenance cost impacts
                Operating and maintenance supply impacts
                Changes in overhead costs
             Operating savings and revenue
                Reduced solid waste disposal costs
                Revenues from increased sale of recyclable material
                Revenues from the sale of by products

           Waste Reduction Volume
           Cycle Time
           Product Quality
           Safety

            Figure 8.36      Waste minimization validation worksheet.







                    program is working. New product or process changes should also be evaluated at the
                    onset to ensure that the design minimizes environmental impact. This is easily accom-
                    plished by adding waste minimization review to the new product or process checklist
                    or standard operating procedure.
                      The waste minimization program is a continuing process versus a one-time proj-
                    ect. Generally, the first waste assessment and implemented alternatives will target
                    only the high-volume waste streams. Once these high-volume streams have been
                    reduced, the team can focus on smaller volume waste streams. From a systems
                    standpoint, the ultimate goal of the team is to minimize all input materials into the
                    facility and by-products generated by the facility. The frequency at which the addi-
                    tional waste assessments are conducted will depend on the budget of the company.
                    In general, organizations that conduct assessments 1 to 4 times per year have
                    achieved paybacks. In addition, if there are special circumstances that indicate the