236   Chapter Twelve

















































            Figure 12.15 Guide blade carrier accommodates thermal expansion.
            (Siemens Power Corporation, Milwaukee, Wis. and Erlangen, Germany)

            samples, and corrective measures should be taken to eliminate these
            deposits during future operation.
              When it has been determined that deposits have formed on the inter-
            nal parts of the turbine, three methods may be employed to remove the
            deposits:

            1. Turbine shut down, casing opened, and deposits removed manually
            2. Turbine shut down and allowed to cool, the deposits cracking off
              because of temperature changes