Page 115 -
P. 115

82     Part 1  •  SyStemS analySiS FundamentalS

                                             Expediting can make or break a successful project. The systems analyst has to remain on top
                                         of the situation by managing the project throughout the entire development process. The analyst
                                         needs to make sure that the project costs are managed properly.

                                         Controlling Costs Using Earned Value Management
                                         Once a systems analyst has an approved budget, it is imperative that the analyst keeps it updated
                                         so the project doesn’t exceed the budget as it progresses. The baseline needs to be continually
                                         revised, and all the stakeholders need to be informed.
                                             Often changes occur in the middle of a project. The client may request new features, or new
                                         technologies may be introduced that will change the way the system is developed. No matter
                                         what these changes are, the budget needs to be revised.
                                             One tool available to systems analysts is earned value management (EVM). It is a technique
                                         used to help determine progress (or setbacks) on a project and involves project cost, the project
                                         schedule, and the performance of the project team. The four key measures in earned value man-
                                         agement are:

                                          •  Budget at completion (BAC) is the total budget for the project, from the beginning until
                                             completion. If you are calculating the performance measures for a task, then it is the total
                                             budget for the task.
                                          •  Planned value (PV) is the value of the work that is to be completed on the project (or,
                                             alternatively, the work completed on any task). Since the value of the work completed is
                                             how much effort and money will be put into it, you can think of planned value (PV) as the
                                             budgeted cost of work scheduled.
                                          •  Actual Cost (AC) is the total cost (direct and indirect) incurred in completing the work
                                             on the project (or, alternatively, a task) up to that particular point in time. Another way of
                                             referring to this is actual cost of work performed to date.
                                          •  Earned value (EV) is an estimate of the value of the work performed thus far. Earned value
                                             therefore refers to only the work that has been completed to date. We can calculate earned
                                             value (EV) as follows:
                                                                          EV 5 PV * p
                                             where p is the percentage of the work completed thus far.
                                             Figure 3.27 shows the cost of developing a website over a five-month period. In this exam-
                                         ple, the development of our website is well under way. The budget at completion is the planned
                                         budget of $18,000, the total estimated cost of developing the website at the end of five months. It
                                         is calculated by summing the cost figures in the estimated cost column.
                                             At the end of the first, second, and third months, the actual cost of the project equals the
                                         cumulative estimated cost, but in the fourth month, the actual cost is $17,000 versus the $15,000
                                         from the cumulative estimate column. It is obvious that we are going over our budget.
                                             It appears to be worse. We’ve only completed 50 percent of stage 4 at the end of the fourth
                                         month. That means we’re falling behind in our schedule as the costs are rising.
                                             Let’s see what the damage is. We already know that the budget at completion for the project
                                         is $18,000 and that the actual cost at the end of the fourth month is $17,000. Let’s determine the
                                         planned value and the earned value at this time.



                                    At the  Stage   Estimated  Cumulative Estimated  Stage  Actual Cost of  Actual Cost of
                                    end of            Cost     Estimate  Duration  Completed  Stage to Date  Project to date
                                   Month 1  Stage 1  $6,000     $6,000   1 month     100%        $6,000        $6,000
                                   Month 2  Stage 2   3,000      9,000   1 month     100%         3,000         9,000
                                   Month 3  Stage 3   3,000     12,000   1 month     100%         3,000        12,000
                                   Month 4  Stage 4   3,000     15,000   1 month      50%         5,000        17,000
                                   Month 5  Stage 5   3,000     18,000   1 month       0%   Not yet begun  Not yet begun

                                 Figure 3.27
                                 The anticipated cost of a website development project over a five-month period.
   110   111   112   113   114   115   116   117   118   119   120