Page 114 -
P. 114

ChaPter 3  •  ProjeCt management     81


                      Eligible   Activity    Time for Each Path  Cost    Cumulative             Figure 3.26
                     Activities   Chosen      22 19 19 16                   Cost                Using expediting to minimize
                                                                                                project time.
                    A, B, D, or I   B         21 18 19 16       $ 500      $ 500

                    A, B, D, or I   B         20 17 19 15        500        1000
                    A, D, or I      I         19 17 18 15        600        1600

                    A or D          A         18 16 18 15        800        2400
                    A and C, or D   D         17 16 17 15       1000        3400

                    A and C, or D   D         16 16 16 15       1000        4400
                    A and C         A and C   15 15 15 14       1200        5600



                     The maximum number of weeks each activity can be reduced is the difference between the
                 expected time and its crash time. For example, activity B, administering questionnaires, could
                 be reduced from four weeks to two weeks at a cost of $500 per week, but it cannot be reduced
                 less than 2 weeks; activity H, preparing the proposal, cannot be reduced because it is already at
                 its crash time.
                     The expediting analysis for this example is provided in Figure 3.26. The expediting process
                 takes place one step at a time, until it is impossible to expedite any further. The columns in the table
                 include eligible activities (tasks that are on the critical path and can be reduced by expediting), the
                 activity chosen (because it is the cheapest alternative), the time it currently takes to complete each
                 of the paths, the cost of expediting the chosen activity, and finally the cumulative cost.
                     In the first step, the critical path is 10–20–30–50–60–70–80, so the eligible activities are
                 A, B, D, and I. Activities G and H are also on the critical path, but they are already at their
                 crash times and are consequently ineligible for expediting. The cheapest alternative is to expe-
                 dite activity B by one day, which reduces the first path from 22 to 21 weeks and the second from
                 19 to 18 weeks; the third and fourth paths are not affected by the reduction since activity B is not
                 on either of those paths.
                     The critical path, and therefore the entire project, is reduced from 22 to 21 weeks (circled on
                 the table). We can repeat this reduction and reduce the project time by another week.
                     When activity B reaches its crash time, another activity must be chosen. Row 3 in the table
                 shows that activities A, D, and I are eligible, and activity I is the cheapest alternative. Reducing
                 activity I reduces not only the critical path but all paths because it is common to all of them.
                     In the fourth step, activity A is chosen, reducing paths 1 and 2, but as a result, there are now
                 two critical paths. This implies that any reduction of the project time will take place only if both
                 of the critical paths are reduced at the same time.
                     We can shorten both paths in the fifth and sixth steps by choosing either a combination of
                 activities A and C (one activity from each of the critical paths) or activity D (an activity common
                 to both critical paths). Reducing activity D by 2 days shortens the paths to 16, 16, 16, and 15
                 days, respectively, and now there are three critical paths.
                     Finally, when activity D reaches its crash time, the only available choice is a combination
                 of activities A and C. The minimum project time is therefore 15 weeks, obtainable by reducing
                 activity A by 2 days, activity B by 2 days, activity C by 1 day, activity D by 2 days, and activity
                 I by one day, at a total cost of $5,600.
                     This example describes all-out expediting to obtain the minimum project time at any cost.
                 But a systems analyst may be faced with a budget. In our example, a budget of $4,000 would
                 result in expediting up to and including step 5. The project would be shortened from 22 to 17
                 weeks, at a cost of $3,400.
                     Another possible criterion would be the net amount that could be saved if the project were
                 shortened. Suppose that in the above example, the analyst would save $750 per week, mostly
                 consisting of the opportunities available for the project team to begin new projects sooner. In
                 this case, expediting would take place until step 3, since the incremental cost of step 4 ($800 for
                 expending activity A) would exceed the $750 saved.
   109   110   111   112   113   114   115   116   117   118   119