Planning and  launching the TPM pilot  161



                   Given below are ‘Terms of Reference’ for the XYZ Company TPM Steering Group.
                   The Group should comprise no more than six members.

                      To provide the Executive with a regular TPM Progress update
                      To communicate and co-ordinate the TPM Activity at the XYZ Company
                      To establish the level of resource and infrastructure to support the TPM Activity and agree
                      the key success factors
                      To set up and monitor the necessary TPM and CAN DO Audit & Review and Measurement
                      Process
                      To establish common TPM and CAN DO Training Programmes, Materials, Procedure and
                      Completion Criteria (from Pilots + Roll Out + Continuous Improvement)
                      To ensure a regular and detailed update of the TPM Pilot Projects and CAN DO Improvement
                      Zone Progress
                      To ensure that any roadblocks to Progress are addressed, action agreed and resolved
                      To confirm TPM Pilot Meeting dates are set and to ensure that these meetings take place and
                      that equipment is released for any essential planned refurbishment
                      To establish the TPM Policy & Procedure for the XYZ Company operations


                  Figure 7.27 Steering Group terms of  reference






                                  Secure management commitment   Trial and prove the route











                   Training - 4-day
                   workshop & key                        4         F
                   contacts













                   Figure 7.28 Typical TPM timetable plan