Page 362 - The Engineering Guide to LEED-New Construction Sustainable Construction for Engineers
P. 362

A S y s t e m a t i c V i e w o f G r e e n a n d M i n i m u m P r o g r a m Re q u i r e m e n t s   323

             before it is constructed, not constructed before it is designed. CPMs are usually depicted
             as diagrams with interconnected arrows. If the activity is listed on the arrow, then it is
             referred to as an “activity on the arrow” CPM, and if the activity is depicted in a box
             between arrows, then it is referred to as an “activity on the node” CPM. Time can be
             included in the CPM schedule by either listing time requirements with the activity or
             placing the activity on a figure similar to the bar chart where time is depicted on the
             horizontal axis. The term critical path method comes from the act of adding time along
             any path of arrows and determining the path which would take the longest time. The
             activities along this path are considered critical since any delay in them will potentially
             delay the completion of the entire project scheduled.
                 CPMs can be evaluated manually or with many established project scheduling
             programs. Some programs are simple, and others are quite complex and include
             additional opportunities to relate many features to each activity such as the workforce
             needs or material needs. Adding these is usually referred to as resource loading. Other
             versions add opportunities for delayed actions or only partial completion of activities
             before the next starts. CPMs are frequently used and are considered to be valuable
             tools in project management. Figure 8.1.1 depicts a very simplified CPM of the activities
             listed in Table 8.1.3 in the activity on the node format with some delayed or early starts
             and finishes on some of the activities. This is done because some of the activities within
             a node may start before a predecessor is totally complete. Determination of the critical
             path would need to include these delayed or early start activity estimates.
                 Scheduling is even more important for several reasons in sustainable construction.
             First, the additional activities needed to design, collect data, and verify systems, etc.,
             which are a part of the LEED process must be integrated into the design and
             construction schedules. There may be cost or schedule conflicts if many of the LEED
             related activities are not performed in a timely fashion. The second reason pertains to
             a more detailed scheduling level.  As noted in Chap. 6 on indoor environmental
             quality, if construction activities are not scheduled in special ways, there are
             opportunities for impacts to indoor air quality such as with mold or particulate matter.
             Scheduling is one of the five principles of SMACNA for good indoor air quality. This
             is the same for many other activities such as erosion and sedimentation control. If the
             sediment fence is not installed on a graded site prior to a storm event, then major





















             FIGURE 8.1.1  Simplifi ed CPM schedule for some major construction project activities with
             some overlapping starts and fi nishes. (Overall activity time in months is given.)
   357   358   359   360   361   362   363   364   365   366   367