Page 208 - The Six Sigma Project Planner
P. 208

+
                                                 +
                                              10 20 30     60
                                                         =    =  20 weeks
                                                   3        3
                    The average doesn’t tell the whole story, either. The benefits will begin as soon as a
                    project is completed; by the end of the 30-week period, project A will have been
                    completed for 20 weeks and project B for 10 weeks.
                    Now let’s consider a multitasking strategy. Here we split our time equally among the
                    three projects in a given 10-week period. That way the sponsor of projects B and C will
                    see activity on their projects much sooner than if we used a single-task approach to
                    scheduling. The new schedule looks like this:

                                    A     B      C     A      B     C      A     B      C

                    With this multitasking schedule, project A will be completed in 23.3 weeks, project B in
                    26.7 weeks, and project C will still take 30 weeks. The completion time for project A
                    went from 10 weeks to 23.3 weeks, for project B it went from 20 weeks to 26.7 weeks,
                    and for project C it remained the same, 30 weeks. The overall average completion time
                    went from 20 weeks to 26.67 weeks, a 33% deterioration in average time to complete.
                    And this is a best-case scenario. In real life, there is always some lost time when making
                    the transition from one project to another. The Black Belt has to switch gears, review the
                    next project, get the proper files ready, reawaken sponsors and team members, and so
                    on. This can often take considerable time, which is added to the time needed to
                    complete the projects.

                    Critical Chain Project Portfolio Management
                    Critical chain project management avoids the multitasking problem by changing the
                    way the organization manages groups of projects and the way the individual projects
                    are managed.

                    Managing the Organization’s Projects
                    First, at the organizational level, multitasking of key resources is stopped. People and
                    other resources are allowed to focus on projects one at a time. This means that
                    management must accept responsibility for prioritizing projects and policies must be
                    developed that mandate single-project focus and discourage multitasking. To be
                    successful, the organization must determine its capacity to complete projects. Every
                    organization has more opportunities than it can successfully pursue with finite
                    resources. This means that only a select portfolio of projects should be undertaken in
                    any time interval. The constraining resource is usually a key position in the
                    organization, such as the time available by project sponsors, engineers, programmers,
                    etc. This information can be used to determine organizational capacity and to schedule
                    project start dates according to the availability of the key resource. This is called project
                    launch synchronization and the scarce resource that paces the project system is called a
                    synchronizer resource.




                                                             191
   203   204   205   206   207   208   209   210   211   212   213