Page 207 - The Six Sigma Project Planner
P. 207

throughput, then it can be considered to be a constraint. For example, if an upstream
                    process average yield is enough to feed the constraint on the average, it may still present
                    a problem. An upstream process producing 20 units per day with an average yield of
                    90% will produce, on average, 18 good units. If the constraint requires 18 units, things
                    will be OK about 50% of the time, but the other 50% of the time things won’t be OK.
                    One solution to this problem is to place a work-in-process inventory between the
                    process and the constraint as a safety buffer. Then on those days when the process yield
                    is below 18 units, the inventory can be used to keep the constraint running. However,
                    there is a cost associated with carrying WIP inventory. A Six Sigma project that can
                    improve the yield will reduce or eliminate the need for the inventory and should be
                    considered even if it doesn’t impact the constraint directly, assuming the benefit-cost
                    analysis justifies the project. On the other hand, if an upstream process can easily make
                    up any deficit before the constraint needs it, then a project for the process will have a
                    low priority.
                    Knowing the project’s throughput priority will help you make better project selection
                    decisions by helping you select from among project candidates. Of course, the
                    throughput priority is just one input into the project selection process; other factors may
                    lead to a different decision. For example, impact on other projects, a regulatory
                    requirement, a better payoff in the long term, etc.


                    Multitasking and Project Scheduling
                    A Six Sigma enterprise will always have more projects to pursue than resources to do
                    them. The fact that resources (usually Black Belts or Green Belts) are scarce means that
                    projects must be scheduled, i.e., some projects must be undertaken earlier than others.
                    In such situations, it is tempting to use multitasking of the scarce resource. Multitasking
                    is defined as the assignment of a resource to several priorities during the same period of
                    time. The logic is that by working on several projects or assignments simultaneously,
                    the entire portfolio of work will be done more quickly. However, while this is true for
                    independent resources working independent projects or subprojects in parallel, it is not
                    true for a single resource assigned to multiple projects or interdependent tasks within a
                    project.

                    Consider the following situation. You have three Six Sigma projects: A, B, and C. A
                    single-tasking solution is to first do A, then B, and then C. Here’s the single-activity
                    project schedule.

                                            A                 B                C
                                     Complete in Week 10  Complete in Week 20  Cmplete in Week 30



                    If each project takes 10 weeks to complete, then A will be completed in 10 weeks, B in 20
                    weeks, and C in 30 weeks. The average time to complete the three projects is calculated
                    as follows:




                                                             190
   202   203   204   205   206   207   208   209   210   211   212