Page 155 - The Toyota Way Fieldbook
P. 155

132                       THE TOYOTA WAY FIELDBOOK


            In Chapters 4 and 5 we discussed the need to isolate variation so that stan-
        dardization may be achieved. The following case example illustrates the challenge
        of standardizing a task with built-in variation. In these cases, before the task can
        be standardized the variation must be separated or isolated from the remaining
        portion, which can then be standardized.


                Case Example: One Job, Three Different Tasks
                The “job” in this case example is to operate two automatic screw
                machines, which cut and machine long bars of steel into discrete metal
                parts. The operator’s work includes three distinctly different tasks. The
                variation inherent in the three tasks makes the job nearly impossible to
                standardize.
                The first task is to perform in-station quality checks and serve the
                machine (removing metal chips and moving finished product). The
                operator is required to perform a specific number of part inspections
                each hour. The inspections are repeatable in nature, and the task is
                repeated within a one-hour time frame (a standard cycle time).

                The second task involves loading raw material as needed. This task is
                also repeatable in nature, but the cycle time varies, based on the part
                being produced and the cycle time of each part produced. The time
                variation is between one and two hours.
                The third task is to set up and change tooling when worn and between
                product changes. This portion of the job is not repeatable within
                several hours, and the frequency of this event is highly variable.
                The tasks range from fairly repeatable and consistent to very variable
                and inconsistent. When blended into one job, it is not possible to
                determine a repeatable pattern that can be standardized. To complicate
                matters, each operator is responsible for two machines. If one machine
                is in setup and the other needs material, the machine in setup will wait.
                If both machines are in setup simultaneously, one machine will wait for
                attention. In many cases this lost time exceeded several days. If both
                machines were operating normally, the first task was not enough to fully
                occupy the operators’ time and they had considerable waiting time. This
                scenario created waiting time for both the operator and the machine.
                To isolate variation, the work tasks were reassigned. The first task was
                assigned to one person who was now responsible for servicing 10
                machines and performing the quality checks. The loading of material
                was assigned to one operator who was responsible for 10 machines,
                and the setup responsibility was assigned to two people for all 10
                machines. This reassignment “freed up” an operator, and the team
                leader role was created to provide additional support to the line.
   150   151   152   153   154   155   156   157   158   159   160