Page 432 - The Toyota Way Fieldbook
P. 432

Chapter 19. Lean Implementation Strategies and Tactics           405


                distributions, box plots, and a four-way probability plot. Also, more
                traditional lean tools were used, such as listing the process steps and
                determining which could be done externally while the machine was
                running and which had to be done internally while the machine was
                down. These activities were prioritized, from those taking the most
                time to those taking the least. A fishbone diagram of the materials,
                man, methods, machine, measurement, and environment causal
                factors effecting inefficient changeovers was developed. The top two
                causal factors were identified as waiting for a changeover cart and the
                process of heating the die, which accounted for 38 percent of the
                changeover time, or 1.3 hours per changeover. They also discovered 12
                of 22 other steps that could be done while the machine was running
                (external).
                The Black Belt in training generated a brainstorm of ideas for
                improvement with some input from the floor. This was narrowed
                down to action items to be implemented:

                ◆ Schedule mold changes to coincide with lunch breaks so the dies
                  could be heated during lunch (they could not justify the cost of
                  equipment to preheat the dies).
                ◆ Add one additional cart, which would be enough to optimize the
                  carts needed.

                ◆ Assign a dedicated changeover team instead of asking operators to
                  do it, so they could prepare a lot of the external changeover items
                  while the machines were running.
                The results exceeded the goal. Detailed data were collected, put on
                run charts and statistically analyzed. It showed significant improve-
                ments. The result was a 98 percent improvement resulting in 2,828
                parts per million defects (defining a  defect as a changeover taking
                more than 2.5 hours). The average changeover took 1.2 hours, well
                below the 2.5 hour target. Analysis of the savings focused on the
                reduced amount of labor for changeovers, which amounted to almost
                $300,000 per year. Actually, the number of changeovers done in a
                week was over the budgeted number, and they had a parallel program
                to stabilize the schedule and reduce the number of changeovers. So
                there were arguments about whether her project should get credit for
                the labor savings based on the current number of changeovers or on
                the anticipated reduced number of changeovers.
                So this was a big success, right? Or was it? Let’s consider what’s
                wrong with this picture:
                1. The total process took several months. Much of that time was
                   spent on sophisticated statistical analysis and preparation of
   427   428   429   430   431   432   433   434   435   436   437