Page 212 -
P. 212

10: Green IT Case Studies for Universities and a Large Company  177



                As the IT organization should also set a good example for its own cus-
             tomers by demonstrating implementation of its strategy within its own
             resources, the IT organization should virtualize the systems management
             servers in the subject data center. We created a project to virtualize those
             servers and submitted the project in the Fall plan for 2008 implementation.
             We received funding for this project, and have begun implementing the
             project creating standard deliverables for how to build and maintain the
             internal infrastructure virtual images.


             Step 4. Manage and Measure
                The next step was to implement power management software. Previously,
             a data center space request tool was implemented that allowed the accounts
             to indicate when they had new data center requirements. This tool was
             enhanced to not only handle space requests but also to determine the power
             and cooling requirements. The management system was enhanced to report
             on power (utility, UPS, and generator), space, and cooling.
                Prior to the physical resources being constrained, the name-plate power
             for the equipment was used for planning. The name-plate power was a con-                          ptg
             servative estimate of the amount of power needed to run a fully configured
             system. Unfortunately, many of the servers we ordered were not fully config-
             ured, causing us to oversize the power and cooling requirements. Equipment
             manufacturers recognized this problem and have provided power calculators
             that allowed us to more accurately size the power requirements because the
             calculators enabled us to specify equipment that was not fully configured.
                This improvement still represented an overstatement of our power usage,
             as many servers do not use maximum power at all times. For example, power
             supplies do not use all their power when the servers are not running at maxi-
             mum utilization. To improve the accuracy of the power consumption, we
             worked with our real estate organization to provide us with monthly meas-
             urements of the actual amount of electricity consumed in the data center.
                The IT team started basing demand on actual data versus estimated data.
             There was still the concern on what percentage of name-plate power we
             should use to size new requests. Analysis was performed on the power usage
             of the existing equipment. The analysis team determined that using an over-
             all 60 percent of name-plate power would provide more accurate sizing than
             the 80 percent they had previously used for new demand requests.
                As equipment manufacturers implement the energy savings features we
             are familiar with in notebook computers (along with new server-based energy
   207   208   209   210   211   212   213   214   215   216   217