Page 208 -
P. 208

10: Green IT Case Studies for Universities and a Large Company  173



                In 2008, The Green Grid modified the PUE metric to make it simpler to
             understand. The new metric is called  Data Center Infrastructure
             Effectiveness (DCiE). The following graphic (see Figure 10.3) describes
             both metrics.
                  DCiE— Data Center (Infrastructure) Efficiency

                  PUE— Power Usage Effectiveness

                                 IT Equipment Power               1
                  DCiE =                                     =
                              Total Raised Floor Power           PUE


                                    Raised Floor Load
                                      Demand from Grid

                                           Power                 IT Load
                                         (UPS, Switchgear,      (Demand from
                                        Transformers, Lights,     Servers,
                                        Battery Back-up, Etc.)  Storage, TELCO
                                                                 Equipment,
                                           Cooling                Etc…)                                        ptg
                                        (CRAC Units, AHUs,
                                         Chillers, Pumps,
                                         Cooling Towers,
                                           Humidifies,
                                         Ventilation, Etc.)



             Source: IBM Green Data Center
             Figure 10.3 Data center metrics DCiE and PUE
                The PUE of 1.8 translated to a DCiE of 0.56, meaning 56 percent of the
             power coming into the data center was going to IT equipment.

             Step 2. Build

                The subject data center resided in a leased facility. As the landlord did not
             want to make significant improvements, the options were limited. The deci-
             sion was made to limit the amount of build activity of new data center space
             because the parking lot was not considered a viable option.
                Fortunately, the “Build” step includes upgrading some of the constrained
             components other than space. In this case, additional power could be added.
             The additional power enabled the replacement of servers with servers of the
             same size but more compute capacity; therefore, the amount of space
   203   204   205   206   207   208   209   210   211   212   213