Page 124 - Trenchless Technology Piping Installation and Inspection
P. 124

90     Cha pte r  T w o

                  8.1.1   Resin impregnation—The quantity of resin used for
                       tube impregnation shall be sufficient to fill the vol-
                       ume of air voids in the tube with additional allow-
                       ances for polymerization shrinkage and the potential
                       loss of resin during installation through cracks and
                       irregularities in the original pipe wall, as applicable.
                  8.1.2   Tube insertion—The wet out tube shall be positioned
                       in the pipeline using either inversion or a pull-in
                       method as defined within relevant ASTM standards
                       previously stipulated. If pulled into place, a power
                       winch or its equivalent should be utilized and care
                       should be exercised not to damage the tube as a result
                       of pull-in friction. The tube should be pulled-in or
                       inverted through an existing manhole or approved
                       access point and fully extend to the next designated
                       manhole or termination point.
                  8.1.3   Temperature gauges shall be placed between the tube
                       and the existing pipe’s invert position to monitor the
                       temperatures during the cure cycle.
                  8.1.4   Curing shall be accomplished by utilizing hot water
                       under hydrostatic pressure or steam pressure in
                       accordance with the manufacturer’s recommended
                       cure schedule.
            9.  Reinstatement of branch connections
             9.1    It is the intent of these specifications that branch connections
                  to buildings be reopened without excavation, utilizing a
                  remotely controlled cutting device, monitored by a CCTV.
                  The contractor shall certify a minimum of two complete func-
                  tional cutters plus key spare components are on the job site
                  before each installation or are in the immediate area of the
                  jobsite and can be quickly obtained. Unless otherwise directed
                  by the owner or his authorized representative, all laterals will
                  be reinstated. No additional payment will be made for exca-
                  vations for the purpose of reopening connections and the
                  contractor will be responsible for all costs and liability associ-
                  ated with such excavation and restoration work.
          10. Inspection
             10.1   CIPP samples shall be prepared for each installation desig-
                  nated by the owner/engineer in accordance with ASTM
                  F1216-09, Sec. 8.1. Pipe physical properties will be tested in
                  accordance with ASTM F1216-09 or ASTM F1743-08, Sec. 8.
                  The flexural properties must meet or exceed the values
                  listed in the Table 2.7∗ of this specification, Table 1 of ASTM

          ∗Please see “Table 2.7. Minimum CIPP Cured Polyester Composite Physical
          Properties”
   119   120   121   122   123   124   125   126   127   128   129