Page 125 - Trenchless Technology Piping Installation and Inspection
P. 125

Existing Pipeline Renewal and Replacement Methods        91

                  F1216-09, or the values submitted to the owner/engineer
                  by the contractor for this project’s CIPP wall design, which-
                  ever is greater.
             10.2   Wall thickness of samples shall be determined as described
                  in paragraph 8.1.6 of ASTM F1743-08. The minimum wall
                  thickness at any point shall not be less than 87 ½ percent of
                  the submitted minimum design wall thickness as calculated
                  from the parameters in paragraph 5.6 of this document.
             10.3   Visual inspection of the CIPP shall be in accordance with
                  ASTM F1743-08, Sec. 8.6.

          11. Clean-up
             11.1   Upon acceptance of the installation work and testing, the
                  contractor shall restore the project area affected by the
                  operations to a condition at least equal to that existing
                  prior to the work.

          12. Payment
             12.1   Payment for the work included in this section will be in
                  accordance with the prices set forth in the proposal for the
                  quantity of work performed. Progress payments will be
                  made monthly based on the work performed during that
                  period.
   120   121   122   123   124   125   126   127   128   129   130