Existing Pipeline Renewal and Replacement Methods 91
F1216-09, or the values submitted to the owner/engineer
by the contractor for this project’s CIPP wall design, which-
ever is greater.
10.2 Wall thickness of samples shall be determined as described
in paragraph 8.1.6 of ASTM F1743-08. The minimum wall
thickness at any point shall not be less than 87 ½ percent of
the submitted minimum design wall thickness as calculated
from the parameters in paragraph 5.6 of this document.
10.3 Visual inspection of the CIPP shall be in accordance with
ASTM F1743-08, Sec. 8.6.
11. Clean-up
11.1 Upon acceptance of the installation work and testing, the
contractor shall restore the project area affected by the
operations to a condition at least equal to that existing
prior to the work.
12. Payment
12.1 Payment for the work included in this section will be in
accordance with the prices set forth in the proposal for the
quantity of work performed. Progress payments will be
made monthly based on the work performed during that
period.