Page 122 - Trenchless Technology Piping Installation and Inspection
P. 122

88     Cha pte r  T w o

                  samples for testing shall be of tube and resin system similar
                  to that proposed for actual construction. It is required that
                  CIPP samples with and without plastic coating meet these
                  chemical-testing requirements.
               6.2   Hydraulic capacity—Overall, the hydraulic cross-section
                  shall be maintained as large as possible. The CIPP shall
                  have a minimum of the full flow capacity of the original
                  pipe before rehabilitation. Calculated capacities may be
                  derived using a commonly accepted roughness coefficient
                  for the existing pipe material taking into consideration its
                  age and condition.
               6.3   CIPP field samples—When requested by the owner, the
                  contractor shall submit test results from field installations
                  of the same resin system and tube materials as proposed for
                  the actual installation. These test results must verify that
                  the CIPP physical properties specified in Sec. 5.5 have been
                  achieved in previous field applications. Samples for this
                  project shall be made and tested as described in Sec. 10.1.
            7.  Installation responsibilities for incidental items
               7.1   It shall be the responsibility of the owner to locate and des-
                  ignate all manhole access points open and accessible for the
                  work, and provide rights-of-access to these locations. If a
                  street must be closed to traffic because of the orientation of
                  the sewer, the owner shall institute the actions necessary to
                  provide access during this for the mutually agreed time
                  period. The owner shall also provide free access to water
                  hydrants for cleaning, installation and other process related
                  work items requiring water.
               7.2   Cleaning of sewer lines—The contractor, when required,
                  shall remove all internal debris out of the sewer line that
                  will interfere with the installation of CIPP. The owner shall
                  also provide a dumpsite for all debris removed from the
                  sewers during the cleaning operation. Unless stated other-
                  wise, it is assumed this site will be at or near the sewage
                  treatment facility to which the debris would have arrived in
                  absence of the cleaning operation. Any hazardous waste
                  material encountered during this project will be considered
                  as a changed condition.
               7.3   Bypassing sewage—The contractor, when required, shall
                  provide for the flow of sewage around the section or sec-
                  tions of pipe designated for repair. Plugging the line at an
                  existing upstream manhole and pumping the flow into a
                  downstream manhole or adjacent system shall make the
                  bypass. The pump(s) and bypass line(s) shall be of adequate
                  capacity to accommodate the sewage flow. The owner may
                  require a detail of the bypass plan to be submitted.
   117   118   119   120   121   122   123   124   125   126   127