Page 229 - Trenchless Technology Piping Installation and Inspection
P. 229

Pr oject Considerations for Horizontal Dir ectional Drilling   193

          should be noted that in Maxi-HDD operations, due to the larger size,
          and greater stiffness of product pipes being installed, the minimum bore
          path radius of curvature may depend on the product pipe diameter.

          Maxi Horizontal Drilling Rig
          Equipment required for a typical Maxi-horizontal drilling operation
          can be transported to the job site in approximately seven tractor-trailer
          loads. A workspace of 100 ft by 150 ft is typical (Fig. 5.4a) at the drill
          rig side. A similar size area at the bore path exit (pipe entry), plus a
          50 ft wide segment of sufficient length to accommodate the assembled
          pipe and associated equipment and handling (see “Product Pipeline
          Fabrication” section below, and as indicated in Fig. 5.4b), will be ade-
          quate for most operations. If necessary, the workspace at the drill rig
          side for HDD equipment may be reduced to a minimum of 60 ft by 150
          ft, but this would restrict the size and capacity of the drilling rig. Space
          requirements will vary depending on the make and model of the drill-
          ing rig and the position of the various components. However, the
          locations of the principal components (drill rig carriage, drill rod, and
          control trailer) are fixed by the entry point. The rig carriage must be
          positioned in line with the drilled segment and close to the entry point.
          The control trailer and drill rod must be positioned adjacent to the rig.
             The workspace must be cleared and graded level. The related
          equipment is typically supported on the ground surface. Timber mats
          may be used where soft ground is encountered.

          Product Pipeline Fabrication
          Pipeline fabrication is accomplished using the same construction meth-
          ods employed to lay a pipeline in a trench, therefore requiring similar
          workspace. The location of the fabrication workspace is controlled by
          the drilled segment exit point. Space must be available to allow the
          pipe to be fed into the drilled borehole. It is preferable to have work-
          space in line with the drilled segment and extending back from the exit
          point the length of the assembled pipeline plus 200 ft. This will allow
          the pipeline to be prefabricated in a single continuous length prior to
          installation. If sufficient space is not available, the pipeline may be
          assembled in several sections, to be welded or fused together during
          installation, or restraint joints can be used (see Chap. 4).
             This workspace must also be cleared, but need not be graded level.
          Equipment is typically supported on the ground surface. Timber mats
          may be used where soft ground is encountered. Figure 5.4b provides
          additional information describing the pipe side of the operation.

          5.3.4 Drilling Fluids
          The primary functions of drilling fluids in Maxi-HDD systems include
          cutting or jetting of soft soils, transmission of rotary power to a mud
          motor, cleaning of cutters, cooling of downhole tool and electronics, trans-
          portation of suspended cuttings, stabilization of the drilled borehole
   224   225   226   227   228   229   230   231   232   233   234