266    Chapter Fourteen
         Exhibit 14-2       Project:
         Field information  Date Originated:
         memo (FIM).
                            FIM No.:
                            Originating Party:
                            Description of field condition












                            Responding Party:
                            Date responded to:

                            Description of resolution:















                                in nature, and that require immediate attention in order to allow the project to
                                progress. Exhibit 14-2 is a sample FIM.
                             3. List of contract drawings and specifications—This is a definitive list of drawings
                                and specifications that define the scope of work for the contractual requirements of
                                the project.
                             4. List of addendums—Addendums are often issued during the bid and award period
                                to clarify details and respond to information requested by the bidders.
                             5. List of bulletins—Bulletins are issued after the award of the project. Bulletins
                                define a change in the work, which must be priced and submitted as a change order
                                for review and approval.
                             6. List of sketches—Sketches are sometimes utilized as an interim means of initiat-
                                ing a change in the work by the owner or design team, which is not extensive to
                                warrant the issuance of a bulletin. Sketches are usually then incorporated into the
                                next bulletin when issued.
                             7. Shop-drawing log—Both the construction manager and design team to track the
                                submission of all shop drawings by each subcontractor specialty will maintain
                                shop-drawing logs. Shop drawings are the basis upon which the subcontractor will