270 Chapter Fourteen
Exhibit 14-5 PROJECT: _________________________________________
OWNER: __________________________________________ PROJECT NO. _____________
General progress
CONTRACTOR: ____________________________________ CONTRACT NO. ___________
report. PROJECT MANAGER: _______________________________ DATE: ____________________
Amount of Original Contract ………………………………………………….. $
Approved Change Orders to Date ……………………………………………
Anticipated Over-run or (Under-run) in Uncompleted Work ……………….
Actual Over-run or (Under-run) in Completed Work ………………………..
Rental Revenue from Contract Owner not included above ………………..
Estimated Total Amount of Principal Contract …………………… . $
Other Contract Work not Included in Principal Contract ……………………
Total Estimated Contract Volume …………………………………. . $
Contract Revenue to Date …………………………………. …… $
Less: Contract Advances for Materials on Hand ……… …….
Contract Advances for Plant and Move-in………. …….
Revenue Reduction for Uncompleted Work ……. …....
Other ………………………………………………..........
Total Amount of Work Completed to Date: … $
Uncompleted Contract Volume ………………………………………………. $
Percent Complete Based on Original Contract ……………………………... __________ %
Percent Complete Based on Total Estimated Contract ……………………. __________ %
Time Allotted by Original Contract …………………………………………… ________ Days
Extension of Contract Time ……...…………………………………………… ________ Days
Total Contract Time ...…...………………………………………….. ________ Days
Contract Time Elapsed ……....…...………………………………………….. ________ Days
Percent of Original Contract Time Elapsed …………………………………. __________ %
Percent of Total Time, Including Extensions, Elapsed …………………….. __________ %
Date Contract was Physically Completed –If Completed ………………….. ____________
Expected Date of Physical Completion –If Not Complete .……………….. ____________