Page 319 - Urban Construction Project Management
P. 319
Project Documentation, Logs, and Reports 273
Exhibit 14-8
Daily equipment
Construction Company Date:
use log.
Address Prepared by:
City, State, ZIP Contractor:
Phone Number Project name:
Weather:
Machine Rate W = Working Total Total
Number Machine per Hr I = Idle Cost Code Hours Cost
W
I
W
I
W
I
W
I
W
I
W
I
W
I
W
I
W
I
W
I
W
I
W
I
W
I
W
I
W
I
W
I
W
I
W
I
W
I
confirm decisions, request dimensions, and clarify field conditions. Exhibit 14-11
contains a sample RFI and Exhibit 14-12 shows a sample RFI log.
28. Inspection and approval reports—These reports document the status of all con-
trolled inspections and approvals required for the project either by the project
specifications or by governing jurisdictional agencies. It is important to track this
information to ensure that the appropriate party who will perform the controlled
inspections and approvals is available in a timely manner, as well as to make the
work available for inspection so as not to impede the progress of the work (see
Chapter 3).
29. Filings and permits—The building department and regulatory filings for the proj-
ect all have associated permits, which need to be tracked to ensure that they are not
outdated, are renewed as required, and are signed off at each phase of the work (see
Chapter 4).