Page 317 - Urban Construction Project Management
P. 317

Project Documentation, Logs, and Reports  271
                                                                                   Exhibit 14-6
           C o  a r t n  r o t c   D a y                   Deta                    Daily log.
                                   J o b  N a m e          Job No
           Field Notes                                     Weather
                                                           Temp
                                                           C  s t f a r  m e n  N o
                                                            Superintendent
                                                             Clerk
                                                             Bricklayers
                                                             Carpenters
                                                             Cement Masons
                                                             Electricians
                                                             Iron Workers
                                                             Laborers
                                                             Operating Engrs
                                                             Plumbers
                                                             Pipe Fitters
                                                             Sheet Metal


                                                           Total
                                                           Equipment     Hrs





           Contract Extras     Authorized By    Amount     Material Purchases




           Equipment Rented Today  From         Rate




           Approved



             are working, number of personnel that are working, weather conditions, and any
             usual events that may have occurred that day. Exhibit 14-6 contains a sample daily
             log.
          22. Daily construction report—This report documents in detail the type of work that is
             being performed by each trade and the overall progress of the project, in more
             detail than the daily log. Exhibit 14-7 contains a daily construction report.
          23. Manpower reports—These reports are utilized to document the number of workers
             in all capacities (foreman, journeyman, apprentices, minority and disadvantaged
             personnel, etc.) that are performing work on the project each day.
          24. Daily equipment use log—This log keeps track of all of the major equipment, mostly
             for logistical purposes, such as the tower cranes, hoist, pumps, bulldozers, lifts, lulls,
             heaters, and crawling cranes. Exhibit 14-8 contains a daily equipment use log.