                                                               Project Documentation, Logs, and Reports  269
                                                                                                 269
                                                                                   Exhibit 14-4
                                                                                   Project photo-
           Construction Company                         Date:                      video log.
           Address                                    Owner:
           City, State, ZIP                        Contractor:
           Phone Number                        Project number:
                                                 Project name:
             Item  Video /     Type
             No.  Photo No Progress  Defect    Description       Date   Taken By




































             project site, along with photographs of each floor. As is often said, “A picture is
             worth a thousand words.” Sometimes a video of the project is also taken to show
             real-time footage of the construction process. Exhibit 14-4 is a sample photo-
             video log.
          20. Progress reports—Progress reports are usually issued on a weekly, semi-weekly, or
             monthly basis to keep the project team informed of the progress of the work. The
             progress report usually contains status of budget, schedule, open items, change
             orders, bids and awards, pending change orders, etc. A sample progress report is
             included in Exhibit 14-5.
          21. Daily log—A daily log is maintained by the superintendent in the field to track the
             progress of the work that day, where work is being performed, which subcontractors