Page 38 - Urban Construction Project Management
P. 38

Project Organization  13
          magnitude basis or by cost per square foot, cost per Btu of cooling or heating, and cost
          per kilowatt of electrical load. Often, allowances may be made where sufficient definition
          of the exact scope of certain items, such as the lobby, plaza, roof garden, and signage is
          not available. In these cases, a target allowance is helpful for the entire project team to
          manage the design and engineering of the area or system. The estimator will usually
          work out of the home office during this phase of the project.

          During the bid and award process, the estimator will be involved with developing the
          list of perspective bidders, screening and finalizing the list of bidders, developing bid
          packages, receiving bids, analyzing and leveling bids, recommending award of subcon-
          tracts, and reviewing the bid for completeness, qualification and exclusions, and unit
          prices (see Chapter 16). This is a very important and critical task; if the subcontractor is
          not scoped out properly and is awarded without a complete project purchase, the amount
          of change orders and claims thereafter can be significant and have a negative impact on
          the project. The estimator will usually work out of the on-site project office for all phases
          of the project.

          During the construction phase, the estimator will be involved with pricing change
          orders for bulletins, sketches, field information memos (FIMs), requests for informa-
          tion (RFIs), and reviewing subcontractor’s claims for extra work as it relates to their
          contracts. All allowances that may have been included in a subcontract need to be
          accounted for and reconciled as the final scope of work and project is defined.

          During the project close-out phase, the estimator will be finalizing all subcontractor
          final contract amounts, including all base contract amounts, approved change orders,
          adjustment of allowances, back charges, etc. to determine the final contract price for
          each subcontractor.


          Scheduler
          The project scheduler is responsible for working with the project team to develop a
          meaningful schedule for the project. All items that are estimated must be scheduled, and
          all items of work that are scheduled must be estimated. This is a good check between
          the estimator and scheduler to ensure a complete scope of work, estimate, and appro-
          priate schedule. During the preconstruction phase of the project, the scheduler will
          develop a conceptual schedule, which will identify the major activities and milestones
          for the project, along with all of the major trades who will be performing work on the
          project. As the design and construction documentation progress, the schedule will be
          refined to include more detail as the sequence of each trades work in each area of
          the project. A schedule will be developed during the bid and award process on which
          all subcontractors will be expected to base their bid and incorporate their activities and
          schedule and sequence of activities accordingly. Once the project is awarded and a con-
          struction base line schedule is established, the scheduler will monitor and report on the
          progress of the work, as it relates to the base line schedule. Major deviations to the
          schedule will be monitored and reported on to ensure that appropriate and timely action
          can be taken to correct a problem before it gets out of hand and there is insufficient time
          and resources to bring the project back on schedule. The scheduler will utilize project
   33   34   35   36   37   38   39   40   41   42   43