Page 257 - Fluid Power Engineering
P. 257

224   Chapter Eleven


              must match demand. Because there is no storage on most networks,
              excess supply or excess demand lead to imbalances. On a second-by-
              second basis, supply and demand are kept in balance with load—
              following spinning reserves generators. On a day-to-day basis, a grid
              operator plans grid operations by seeking day-ahead generation plans
              from each generation entity on the grid. The day-ahead plan, or fore-
              cast, is in the form of an hour-by-hour generation output that will be
              made available to the grid. This is called generator’s schedule. In the
              United States, if a generation entity is unable to supply to the hour-by-
              hour schedule (of the day-ahead plan), then there are penalties. These
              penalties are called imbalance charges; the intent is to encourage ac-
              curate forecasting such that reliability of the system can be enhanced.
              This mechanism works well for fossil fuel-based generators (base-load
              or spinning reserves) because there is no variability in availability of
              raw material. The mechanism does not work well for renewable en-
              ergy sources like solar and wind.
                 An alternate mechanism that favors renewable energy has been
              developed by California Independent System Operator (CAISO),
              which removes penalties based on hour-by-hour schedule and allows
              for netting of schedules at the end of the month. In order to avail of
              this netting, the wind plant operator must participate in the central-
              ized wind output forecasting program through which CAISO pro-
              vides forecasting and scheduling. Other approaches that have been
              floated, not necessarily implemented, are to allow wind plant opera-
                                          3
              tors to provide 4-h ahead forecasts for wind resource and for system
              operators to balance supply and demand at this granularity.

        Single-Line Diagram
              A wind project of a reasonable size requires a diagram to represent the
              various electrical components of the wind project and interfaces with
              the grid. A simple method to achieve this is with a single-line diagram.
              The basic components in a circuit for wind project are seen in Fig. 11-1.
                 Most turbines produce AC power at 480 V (smaller turbines) or
              690 V (utility-scale turbines). In order to minimize losses, this power
              is transformed into distribution-level voltage of 11 to 34.5 kV using a
              transformer at the base of the tower. The circuit on the higher voltage
              side of the transformer is called the medium voltage (MV) circuit. The
              MV circuit consists of switches to disconnect power and underground
              cables to carry the power to a substation. At the substation, the power
              is transformed again and the voltage is lifted to the grid voltage. A
              circuit breaker in the substation monitors the grid parameters and
              compares to the power parameters that are on the output side of the
              substation. The circuit breaker trips when it detects a fault and discon-
              nects the entire wind farm from the grid. Switchgear is a combination
              of fuses, circuit breakers, and others. In this section, the two terms
              circuit breaker and switchgear will be used interchangeably.
   252   253   254   255   256   257   258   259   260   261   262