Page 311 -
P. 311

10.52                      CHAPTER TEN


           A  cryogenic air separation  system consumes about 260 to 340 kWh  (936  to  1,224 MJ)
         of energy  per ton  (1,016  kg)  of oxygen produced,  depending  on the plant  capacity,  with
         about  90%  of it used  by  the  main  compressor.  Because  of its high  power  requirements,
         high-efficiency compressors  and  drives  are required to reduce  the total  operating cost.
           Turndown  of a  cryogenic  air  separation  system  is  limited  primarily  by  the  main  air
         compressor  and  the  distillation  column.  The  maximum  turndown  for  a  single  main  air
         compressor is about  70%  to  75%  of the rated  capacity.  Below that  limit, the compressor
         will  become  unstable  and  must  be  vented.  The  turndown  of a  cryogenic  system  is  also
         limited  by  the  distillation  column  to  about  50%.  Below  50%  of  system  capacity,  GOX
         must be vented or LOX  must  be produced  in order to  maintain  system  stability.
           The turndown  range  can be increased by using multiple trains.  For a two-train system
         with  each train  rated  at  50%  of capacity,  the turndown  can  extend  to  30%  of total rated
         capacity.  However, because  of high capital costs  and  operating  complexity, the selection
         of the number of trains must be based on process requirements rather than turndown range.
           The  response  rate  to  demand  changes  of a  cryogenic  system  is  relatively  slow,  nor-
         mally  about  2%  to  3%  per  minute.  Therefore,  from  100%  to  70%,  it will take  about  10
         to  15 min to reduce the production rate. If one train is shut down but maintained in a cold
         condition  (sometimes  referred  to  as  "bottled  up")  for  less  than  12  h,  the  "cold start-up"
         time to reach  full production  is about  1 to 2 h.  If the  system  is maintained  in cold condi-
         tion for more than  12 h,  the cold  start-up  time will increase  to  2  to  3  h.  If the cryogenic
         system is restarted  from  ambient  temperature,  LOX  is required,  and  the  "warm  start-up"
         time is about  2  to  3  days.
           Providing  redundancy  of equipment  to  ensure  uninterrupted  operation  is  a  common
         practice  for municipal  agencies.  Redundancy  normally  includes  multiple trains  of equal-
         capacity equipment,  with one or two more trains on standby.  However, manufacturers  in-
         dicate that with a sound operation and maintenance  program,  a cryogenic plant can be on-
         line over 98%  of the time without  a  second  train.  They  also  indicate that  a  standby  cold
         box  is  not needed,  because  there  are  no  rotating  parts  in  this  unit.  However, this  would
         require  adequate  LOX  backup  storage  in  the  event of a  cold box  problem.  Redundancy
         of rotating  equipment  and  product  storage tanks  is desirable.
           Noise  levels from  an  air  separation  plant  can  be  high  unless  special  consideration  is
         given during  the  design to reduce  the  noise.  Noise levels from the  main  air compressors
         in general exceed 90 dBa  (decibels  a-weighted)  at a distance  of 3 ft (0.9  m).  Therefore it
         is common to house this equipment in a sound-insulated  enclosure.  A  separate silencer in
         addition  to the  inlet filter/silencer assembly  may  be needed  to reduce  the  noise at the in-
         let of the compressors.  Silencers should be provided at the outlet of the compressor surge
         vent line and  the product  and  waste  vent lines.  Switching  valves would generate  a noise
         level over  100  dBa  at  a  distance  of 3  ft  (0.9  m)  and  should  be  provided  with  an  enclo-
         sure  and  silencer to reduce  the noise.
           Depending  on  the  equipment  size,  sheet  metal  enclosures  with  an  acoustic  treatment
         may  be  required  for  the  booster  compressors  and  gas  product  compressors.  Most liquid
        product  pumps  are  small  and  should  not cause  concern  about  the  noise  level. The  cool-
        ing water pumps  are usually  centrifugal  and  should  have  noise levels below  85  dBa.
           Depending  on  the  size,  the  main  air compressor  may  require  a  power  supply  of 480,
        2,400,  or 4,160  V.  The  remaining  equipment  normally  requires  either  a  120-  or 480-V
        supply.  The  main  air compressor  is  started  unloaded  and  may  take  5  to  15  min to reach
        its  operating  status,  depending  on  compressor  size.  If the  standby  unit  is  started  before
        the  duty  unit  is  shut  down  to  maintain  uninterrupted  air  supply,  the  power  requirement
        should  include the  standby  unit.
           The  cryogenic  plant  requires  large  quantities  of cooling  water  equal  to  8  to  10  gpm
        (30  to  38  L/min) per ton  (907  kg)  of oxygen production.
   306   307   308   309   310   311   312   313   314   315   316