Page 115 -
P. 115

4 - PROJECT INTEGRATION MANAGEMENT






                         •  Scope management plan (Section 5.1.3.1),
                         •  Requirements management plan (Section 5.1.3.2),

                         •  Schedule management plan (Section 6.1.3.1),
                         •  Cost management plan (Section 7.1.3.1),

                         •  Quality management plan (Section 8.1.3.1),                                                    4
                         •  Process improvement plan (Section 8.1.3.2),

                         •  Human resource management plan (Section 9.1.3.1),
                         •  Communications management plan (Section 10.1.3.1),
                         •  Risk management plan (Section 11.1.3.1),

                         •  Procurement management plan (Section 12.1.3.1),
                         •  Stakeholder management plan (Section 13.2.3.1),

                         •  Scope baseline (Section 5.4.3.1),
                         •  Schedule baseline (Section 6.6.3.1), and
                         •  Cost baseline (Section 7.3.3.1).


                   4.4.1.2 Schedule Forecasts


                      Described in Section 6.7.3.2. The schedule forecasts are derived from progress against the schedule baseline
                   and computed time estimate to complete (ETC). This is typically expressed in terms of schedule variance (SV) and
                   schedule performance index (SPI). For projects not using earned value management, variances against the planned
                   finish dates and forecasted finish dates are provided.

                      The forecast may be used to determine if the project is still within defined tolerance ranges and identify any
                   necessary change requests.


                   4.4.1.3 cost Forecasts

                      Described in Section 7.4.3.2. The cost forecasts are derived from progress against the cost baseline and computed
                   estimates to complete (ETC). This is typically expressed in terms of cost variance (CV) and cost performance index
                   (CPI). An estimate at completion (EAC) can be compared to the budget at completion (BAC) to see if the project is
                   still within tolerance ranges or if a change request is required. For projects not using earned value management,
                   variances against the planned versus actual expenditures and forecasted final costs are provided.














                   ©2013 Project Management Institute. A Guide to the Project Management Body of Knowledge (PMBOK  Guide) – Fifth Edition   89
                                                                                       ®


                                           Licensed To: Jorge Diego Fuentes Sanchez PMI MemberID: 2399412
                                       This copy is a PMI Member benefit, not for distribution, sale, or reproduction.
   110   111   112   113   114   115   116   117   118   119   120