Page 168 -
P. 168

148   CHAPTER 4 LINEAR PROGRAMMING APPLICATIONS



                                      Table 4.4 Machine, Labour and Storage Capacities for Bollinger Electronics
                                                  Machine Capacity     Labour Capacity      Storage Capacity
                                      Month            (hours)             (hours)          (square metres)

                                      April             400                  300                10 000
                                      May               500                  300                10 000
                                      June              600                  300                10 000



                                     If the company specifies a minimum inventory level at the end of the three-month
                                     period of at least 400 units of component 322A and at least 200 units of component
                                     802B, we can add the constraints:
                                                                     s 13   400
                                                                     s 23   200
                                       Suppose that we have the additional information on machine, labour and storage
                                     capacity shown in Table 4.4. Machine, labour and storage space requirements
                                     are given in Table 4.5. To reflect these limitations, the following constraints are
                                     necessary.

                                     Machine Capacity
                                                           0:10x 11 þ 0:08x 21   400 Month 1
                                                           0:10x 12 þ 0:08x 22   500 Month 2
                                                           0:10x 13 þ 0:08x 23   600 Month 3

                                     Labour Capacity
                                                           0:05x 11 þ 0:07x 21   300 Month 1
                                                           0:05x 12 þ 0:07x 22   300 Month 2
                                                           0:05x 13 þ 0:07x 23   300 Month 3
                                     Storage Capacity

                                                            2s 11 þ 3s 21   10000  Month 1
                                                            2s 12 þ 3s 22   10000  Month 2
                                                            2s 13 þ 3s 23   10000  Month 3
                                       One final set of constraints must be added to guarantee that I m and D m will
                                     reflect the increase or decrease in the total production level for month m. Suppose
                                     that the production levels for March, the month before the start of the current
                                     production scheduling period, had been 1500 units of component 322A and 1000
                                     units of component 802B for a total production level of 1500 + 1000 ¼ 2500 units.



                                      Table 4.5 Machine, Labour and Storage Requirements for Components 322A
                                      and 802B

                                                          Machine           Labour         Storage (square
                                        Component        (hours/unit)     (hours/unit)       metres/unit)

                                           322A             0.10             0.05                2
                                           802B             0.08             0.07                3






                Copyright 2014 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s). Editorial review has
                      deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.
   163   164   165   166   167   168   169   170   171   172   173