Page 455 -
P. 455

ORDER-QUANTITY, REORDER POINT MODEL WITH PROBABILISTIC DEMAND  435


                                      D/Q* ¼ 8008/400 ¼ 20 orders per year with an average of approximately 250/20 ¼ 12.5
                                      working days between orders.

                                      The When-to-Order Decision
                                      We now want to establish a when-to-order decision rule or reorder point that will
                                      trigger the ordering process. With a mean lead-time demand of 154 units, you might
                                      first suggest a 154-unit reorder point. However, considering the probability of
                                      demand now becomes extremely important. If 154 is the mean lead-time demand,
                                      and if demand is normally distributed about 154, then the lead-time demand will be
                                      more than 154 units roughly 50 per cent of the time. When the demand during the
                                      one-week lead time exceeds 154 units, Dabco will experience a shortage or stock-
                                      out. Thus, using a reorder point of 154 units, approximately 50 per cent of the time
                                      (ten of the 20 orders a year) Dabco will be short of bulbs before the new supply
                      The probability of a  arrives. This shortage rate would most likely be viewed as unacceptable.
                      stock-out during any one
                      inventory cycle is easiest  Refer to the lead-time demand distribution shown in Figure 10.11. Given this
                      to estimate by first  distribution, we can now determine how the reorder point r affects the probability of
                      determining the number  a stock-out. Because stock-outs occur whenever the demand during the lead time
                      of orders that are
                      expected during the year.  exceeds the reorder point, we can find the probability of a stock-out by using the
                      The inventory manager  lead-time demand distribution to compute the probability that demand will exceed r.
                      can usually state a  We could now approach the when-to-order problem by defining a cost per stock-
                      willingness to allow  out and then attempting to include this cost in a total cost equation. Alternatively,
                      perhaps one, two or
                      three stock-outs during  we can ask management to specify the average number of stock-outs that can be
                      the year. The allowable  tolerated per year. If demand for a product is probabilistic, a manager who will
                      stock-outs per year  never tolerate a stock-out is being somewhat unrealistic because attempting to avoid
                      divided by the number of  stock-outs completely will require high reorder points, high inventory and an asso-
                      orders per year will
                      provide the desired  ciated high holding cost.
                      probability of a stock-out.  Suppose in this case that Dabco management is willing to tolerate an average of
                                      one stock-out per year. Because Dabco places 20 orders per year, this decision
                                      implies that management is willing to allow demand during lead time to exceed
                                      the reorder point one time in 20, or 5 per cent of the time. The reorder point r can
                                      be found by using the lead-time demand distribution to find the value of r with a 5
                                      per cent chance of having a lead-time demand that will exceed it. This situation is
                                      shown graphically in Figure 10.12.
                                         From the standard normal probability distribution table in Appendix A, we see
                                      that the r value is 1.645 standard deviations above the mean. Therefore, for the




                                      Figure 10.12 Reorder Point r that Allows a 5 per cent Chance of a Stock-Out for
                                      Dabco Lightbulbs






                                                                                 r
                                                                     No Stock-Out  Stock-Out
                                                                      (demand    r)  (demand > r)
                                                                         95%          5%


                                                            79  104  129  154  179  204  229
                                                                   Lead-Time Demand






                Copyright 2014 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s). Editorial review has
                      deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.
   450   451   452   453   454   455   456   457   458   459   460