Page 51 - Analysis, Synthesis and Design of Chemical Processes, Third Edition
P. 51

Consider the benzene product line leaving the right-hand side of the P&ID in Figure 1.7. The flowrate of
                    this stream is controlled by a control valve that receives a signal from a level measuring element placed
                    on V-104. The sequence of instrumentation is as follows:


                    A level sensing element (LE) is located on the reflux drum V-104. A level transmitter (LT) also located
                    on  V-104  sends  an  electrical  signal  (designated  by  a  dashed  line)  to  a  level  indicator  and  controller
                    (LIC).  This  LIC  is  located  in  the  control  room  on  the  control  panel  or  console  (as  indicated  by  the
                    horizontal line under LIC) and can be observed by the operators. From the LIC, an electrical signal is sent
                    to  an  instrument  (LY)  that  computes  the correct  valve  position  and  in  turn  sends  a  pneumatic  signal
                    (designated by a solid line with cross hatching) to activate the control valve (LCV). In order to warn
                    operators of potential problems, two alarms are placed in the control room. These are a high-level alarm
                    (LAH) and a low-level alarm (LAL), and they receive the same signal from the level transmitter as does
                    the controller.


                    This  control  loop  is  also  indicated  on  the  PFD  of Figure  1.5.  However,  the  details  of  all  the
                    instrumentation  are  condensed  into  a  single  symbol  (LIC),  which  adequately  describes  the  essential
                    process control function being performed. The control action that takes place is not described explicitly in

                    either drawing. However, it is a simple matter to infer that if there is an increase in the level of liquid in
                    V-104, the control valve will open slightly and the flow of benzene product will increase, tending to
                    lower the level in V-104. For a decrease in the level of liquid, the valve will close slightly.


                    The details of the other control loops in Figures 1.5 and 1.7 are left to problems at the end of this chapter.
                    It is worth mentioning that in virtually all cases of process control in chemical processes, the final control
                    element is a valve. Thus, all control logic is based on the effect that a change in a given flowrate has on a
                    given  variable.  The  key  to  understanding  the  control  logic  is  to  identify  which  flowrate  is  being
                    manipulated to control which variable. Once this has been done, it is a relatively simple matter to see in
                    which direction the valve should change in order to make the desired change in the control variable. The
                    response  time  of  the  system  and  type  of  control  action  used—for  example,  proportional,  integral,  or
                    differential—are left to the instrument engineers and are not covered in this text.





                          The final control element in nearly all chemical process control loops is a valve.


                    The P&ID is the last stage of process design and serves as a guide for those who will be responsible for
                    the final design and construction. Based on this diagram,
                          1.   Mechanical engineers and civil engineers will design and install pieces of equipment.

                          2.   Instrument engineers will specify, install, and check control systems.
                          3.   Piping engineers will develop plant layout and elevation drawings.
                          4.   Project engineers will develop plant and construction schedules.


                    Before final acceptance, the P&IDs serve as a checklist against which each item in the plant is checked.

                    The P&ID is also used to train operators. Once the plant is built and is operational, there are limits to
                    what operators can do. About all that can be done to correct or alter performance of the plant is to open,

                    close,  or  change  the  position  of  a  valve.  Part  of  the  training  would  pose  situations  and  require  the
                    operators to be able to describe what specific valve should be changed, how it should be changed, and
   46   47   48   49   50   51   52   53   54   55   56