Page 58 - Analysis, Synthesis and Design of Chemical Processes, Third Edition
P. 58

Therefore, the pipe diameter that satisfies both the heuristic and the continuity equation lies between 3 and
                    4 inches. Taking a conservative estimate, a 4-inch suction line is chosen for P-202.
                               The next step to consider is the placement of equipment within the plot plan. This placement must
                                be made considering the required access for maintenance of the equipment and also the initial
                                installation.  Although  this  step  may  seem  elementary,  there  are  many  cases  [5]  where  the
                                incorrect  placement  of  equipment  subsequently  led  to  considerable  cost  overruns  and  major
                                problems both during the construction of the plant and during maintenance operations. Consider
                                the  example  shown  in Figure 1.10(a), where two vessels, a tower, and a heat exchanger are
                                shown in the plot plan. Clearly, V-1 blocks the access to the exchanger’s tube bundle, which
                                often requires removal to change leaking tubes or to remove scale on the outside of the tubes.
                                With  this  arrangement,  the  exchanger  would  have  to  be  lifted  up  vertically  and  placed

                                somewhere  where  there  was  enough  clearance  so  that  the  tube  bundle  could  be  removed.
                                However,  the  second  vessel,  V-2,  and  the  tower  T-1  are  located  such  that  crane  access  is
                                severely limited and a very tall (and expensive) crane would be required. The relocation of
                                these same pieces of equipment, as shown in Figure 1.10(b), alleviates both these problems.
                                There are too many considerations of this type to cover in detail in this text, and the reader is
                                referred to Bausbacher and Hunt [5] for a more in-depth coverage of these types of problems.
                                Considering the DME facility, a possible arrangement for the feed and reactor subsection is
                                shown in Figure 1.11.


                    Figure 1.10 The Effect of Equipment Location on the Ease of Access for Maintenance, Installation, and
                    Removal
   53   54   55   56   57   58   59   60   61   62   63