290                                                                               Boiler Operator’s Handbook






































































                                                 Figure 10-22. “D” type boiler details


               ing up, there are always different degrees of assembly.  packaged boiler or clearances into a building where the
               When specifying a package water tube boiler an engineer  owner wanted the boiler installed resulted in field erec-
               has to explain very carefully what he calls a package.  tion of those boilers. In the middle 1960’s boilermakers
                    There are also a lot of package boilers setting  working for Power and Combustion felt they were in a
               around that were not built in a factory, they were field  contest to see if they could field erect more Combustion
               erected. Problems of shipping clearances where a bridge  Engineering package boilers than Combustion built in
               or tunnel near a plant prevented delivery of a factory  the factory. I don’t know if that was a close competition