Boiler Plant Operations                                                                              57


               you will be able to tell immediately if the valve is open  even then you can’t be certain that the conditions in
               because they’ll try to close it and it will make at least  your plant are identical to the conditions in the factory.
               a quarter turn toward closed. If you leave the valve  So, the initial start-up of a boiler requires a careful ap-
               jammed open someone can think it’s closed because  proach to lighting the initial fire. You should ensure air
               it doesn’t spin that quarter turn. I was so used to that  flow, make certain it’s linear on modulating boilers and
               practice, and still believe in it, that I’m regularly foiled  establish safe light-off conditions before thinking about
               by someone leaving a valve jammed open. Thank good-  starting to fire.
               ness the important ones have to be rising stem so I can     The codes require a minimum amount of building
               tell their position by looking at them.              opening to admit fresh air for combustion but I’ve found
                                                                    that it’s frequently overlooked. If you’re starting up the
                                                                    only boiler in the plant it’s possible there’s no way for
               NEW START-UP                                         combustion air to enter that boiler room. If the boiler is
                                                                    an addition to an existing plant the likelihood that some-
                    There is a significant difference between starting a  one paid attention to the requirements for combustion
               boiler plant that is new and one that has been in opera-  air is even more remote.
               tion. Hundreds of wiring connections, pipe joints, and     A basic rule is two openings consisting of one square
               other work went into preparing the boiler and there’s  inch in each opening for every 1,000 Btuh of boiler input
               bound to be a few unforeseen problems as the start-up  and a minimum of 100 square inches for small boilers.
               proceeds. These guidelines should help you achieve  Larger installations allow 4,000 Btuh per square inch. One
               a smooth start-up. They should also be used after any  opening should be high up in the building and the other
               maintenance that resulted in opening a system.       near the floor. Prior to starting a new boiler the avail-
                    First, have a written procedure prepared, not an  ability of fresh air should be confirmed and the openings
               outline. Each step should be described along with who  should be labeled “combustion air, do not cover.”
               is responsible for the action. In many cases it will be     I’ve ventured into many a building where the air
               the installing contractor’s responsibility to produce this  openings were blocked because the operators could
               document but you should check it for completeness and  feel a draft. Then they couldn’t understand why their
               accuracy. Imagine the start-up proceeding and try to  boiler was smoking. Once you’ve confirmed the fresh
               imagine all the things that could go wrong as well when  air source make sure you have linear air flow on any
               preparing or checking a written procedure. The follow-  modulating boiler; refer to the chapter on tune-ups for
               ing should be addressed by the written procedure.    establishing linearity.
                                                                        Make sure each fluid system is closed and ready to
               Preparing for Operation                              accept fluids before opening shut-off valves. When pre-
                    Be certain the safety shutdown push-buttons,  paring to admit liquids identify vent valves and make
               switches, valves, and other devices are in place and op-  certain they are open, you can’t put much water in a
               erational. Test each one if possible and refuse to contin-  boiler plugged full of air. If the fluid is admitted through
               ue the procedure if one is not present or not operational.  a pressure reducing station position a person to monitor
                    Check all electrical circuits for shorts and grounds  the pressure in the system.
               before energizing them. Make sure all equipment and      Position observers to detect leaks in the piping and
               piping is electrically grounded before admitting fluids  equipment. Be certain that observers are capable of see-
               into the plant. Energize all electrical circuits before admit-  ing all drains leaving the plant to ensure hazardous or
               ting fluids into the plant to ensure they can be powered  toxic materials don’t escape. Ensure the person control-
               up. Test all electrical emergency trips and shutdown de-  ling the valve(s) admitting the fluid is in contact with
               vices. De-energize circuits before admitting fluids.  all observers and can shut the valves immediately if a
                    Prior to closing a boiler or pressure vessel inspect  problem arises. Ensure personnel are positioned to close
               it to ensure there are no personnel, tools, or other things  vent valves as the system is filled.
               inside that shouldn’t be there. In Amsterdam in 1967 I     Have I said it before? Look at the instruction manu-
               almost closed a boiler with ten shipyard workers nap-  als. Know how much fluid is required to fill the system
               ping in its furnace.                                 and estimate the filling time. It’s another way to ensure
                    Small boilers can come set up from the factory to  you know the fluid is going where it’s supposed to. Won-
               reduce the chances of a problem on initial start-up. It’s  dering where all that fuel oil went several minutes after
               rare that a boiler to be attended is factory tested and  the tank should have been full is not a comfortable feel-