Page 37 - Buried Pipe Design
P. 37

External Loads  15

         TABLE 2.1 Approximate Values of Soil Unit Weight, Ratio of Lateral to Vertical
         Earth Pressure, and Coefficient of Friction against Sides of Trench
                             Unit weight,  Rankine’s ratio  Coefficient of
              Soil type         lb/ft 3      K          friction
         Partially compacted
          damp top soil          90          0.33         0.50
         Saturated top soil     110          0.37         0.40
         Partially compacted
          damp clay             100          0.33         0.40
         Saturated clay         120          0.37         0.30
         Dry sand               100          0.33         0.50
         Wet sand               120          0.33         0.50

         were determined experimentally by Marston, and typical values are
         given in Table 2.1.
           Example Problem 2.1 What is the maximum load on a very rigid pipe in a
           ditch excavated in sand? The pipe diameter (OD) is 18 in, the trench width
                                                                       3
           is 42 in, the depth of burial is 8 ft, and the soil unit weight is 120 lb/ft .
           1. Determine C d . From Table 2.1 for sand, K    K ′   0.165.
                              H     8 ft   12 in
                                                   2.29
                              B d   42 in   1 ft
              From Fig. 2.2, C d   1.6.
           2. Calculate the load from Eq. (2.4):
                                               12  2
                                              42
                                  2
                        W d   C d  B d   1.6 (120)        2352 lb/ft
         Embankment conditions. Not all pipes are  installed  in ditches
         (trenches); therefore,  it  is necessary to treat the problem of pipes
         buried in embankments. An embankment is where the top of the pipe
         is above the natural ground. Marston defined this type of installation
         as a positive projecting conduit. Typical examples are railway and
         highway culverts. Figure 2.4 shows two cases of positive projecting
         conduits as proposed by Marston. In case I, the ground at the sides of
         the pipe settles more than the top of the pipe. In case II, the top of the
         pipe settles more than the soil at the sides of the pipe. Case I was
         called the projection condition by Marston and is characterized by a
         positive settlement ratio r sd , defined as (see Fig. 2.4)

                                           )
                                   ( S +  S − ( S +  d )
                               r =   m    g    f   c
                                sd         S
                                            m
         The shear forces are downward and cause a greater load on the buried
         pipe for this case. Case II is called the ditch condition and is charac-
                                               . The shear forces are directed
         terized by a negative settlement ratio r sd
         upwards in this case and result in a reduced load on the pipe.
   32   33   34   35   36   37   38   39   40   41   42