Page 192 - Chemical Process Equipment - Selection and Design
P. 192

164  FLUID TRANSPORT  EQUIPMENT
                 condensables are removed with a cold water spray. The tail pipes of   such gases is the air leakage from the atmosphere into the system.
                the  condensers are  sealed with  a  34ft leg into  a  sump, or  with  a   Theoretically, the leakage rate of  air through small openings, if
                condensate  pump  operating  under  vacuum.  Surface  condensers   they  can  be  regarded  as  orifices or  short  nozzles,  is  constant  at
                 permit recovery of valuable or contaminating condensates or steam   vessel  pressures  below  about  53%  of  atmospheric  pressure.
                 condensate for return as boiler feed. They are more expensive than   However, the openings appear to behave more nearly as conduits
                 barometrics, and their  design is  more  complex than  that  of  other   with  relatively  large  ratios  of  lengths  to  diameters.  Accordingly
                 kinds  of  condensers because of  the  large  amounts of  nonconden-   sonic flow is approached only at the low pressure end,  and the air
                 sables that are present.                           mass inleakage rate  is determined  by  that  linear velocity and the
                    As  many  as  six  stages  are  represented  on  Figure  7.30,   low density prevailing at the vessel pressure. The content of  other
                 combined with  interstage  condensers in  several ways.  Barometric   gases  in  the  evacuated  vessel  is  determined  by  each  individual
                 condensers are feasible only if the temperature of the water is below   process. The content of condensables can be reduced by interposing
                 its  bubblepoint  at  the  prevailing  pressure  in  a  particular  stage.   a refrigerated condenser between process and vacuum pump.
                 Common practice requires the temperature to be  about 5°F below   Standards have been developed by the Heat Exchange Institute
                 the bubblepoint. Example 7.13 examines the feasibility of installing   for rates of  air leakage into commercially tight systems. Their chart
                 intercondensers in that process.                   is represented by the equation
                 AIR LEAKAGE                                           rn = kVzm,                               (7.59)
                 The size of  ejector and its steam consumption depend on the rate at
                 which gases must be removed from the process. A basic portion of   where rn is in lb/hr, V is the volume of  the system in cuft, and the




                    EXAMPLE 7.11                                    stages  are  estimated  from  Figure  7.29  under  the  assumption of
                    Three-Stage Compression with Intercooling and Pressure Loss   equal compression ratios as zo = 0.98,  z, = 0.93, and z, = 0.83.  The
                    between Stages                                  interstage pressures will be determined on the basis of  equal power
                 Ethylene  is  to  be  compressed  from  5  to  75 atm  in  three  stages.   load in each stage. The estimated compressibilities can be corrected
                 Temperature to the first stage is 60"F, those to the other stages are   after  the pressures have been  found, but  usually this is not found
                 100°F. Pressure  loss between  stages is  0.34 atm  (5 psi).  Isentropic   necessary. k = C,/C,  = 1.228 and (k - 1)/k = 0.1857.
                 efficiency of  each stage is 0.87. Compressibilities at the inlets to the





                                                           -
                             To= 6OF                     P, 0.34
                             Po= 5 atm                   T, = 60
                             &=0.98                      z, =0.93                  ZpO.83


                 With equal power in each stage                     Total power =  3(0.98)(1.987)(520)  12.25  0.1857  -  '1
                                                                                0.1857(2545)0.87  [(T)
                                  0 1857
                                                                              = 1.34 HP/(lb mol/hr).
                       (k-  1)%
                      = 0.98(520)[(P1/5)0.1857 - 11                                            I         I
                                        0.1857
                                                                                 32  -
                      = 0.83(560){(75/(P, - 0.34)]0.1857 - 1)

                    Values of Pl will be assumed until the value of  P2 calculated by
                 equating the first two terms equals that calculated from the last two
                 terms. The last entries in the table are the interpolated values.

                                             e
                                s       1+2     2+3                                                       -
                                                                                             p, -
                               12      27.50    28.31
                               12.5    29.85    28.94                            27           I         I
                               13.0    32.29    29.56                              12       12.5        13
                               12.25      -28.6&
   187   188   189   190   191   192   193   194   195   196   197