7.9 Resource Assignment                                              333






















                             Figure 7.69 Processes to be assigned

































               Figure 7.70 Processes sorted according to their left edge (starting time)





        time earlier than 1. Process D in the only acceptable process in the list. Process G
        has a finishing time that is too late. No more processes can be assigned to the
        second resource. To the third resource we first assign process F and then G.
            Finally, the two remaining processes are assigned to the fourth resource. The
        resulting assignments are shown in Figure 7.71. Note that there are often several
        assignments that yield the same number of resources. Additional criteria may
        therefore be used to select the best among these alternatives.