142   Section Two-FIELD  FABRICATION

            SCHEDULE         4O   CEMENT        LINED      CARBON
            STEEL      PIPE    WITH     STANDARD          FITTINGS

                            MAN  HOURS  PER  UNITS  LISTED

         Pipe     Handle    Cutting     Butt   Sleeve Joint 90° Welded  Smooth  On
         Size      Pipe       Pipe     Welds    With  Two  Nozzle    Cement
         Ins.    Per  Foot  Per Cut    Each    Welds Each   Each     Per Joint

          6          ,40       .65      2.0       3.30       6.05      .35
          8          .50      1.00      2.6       4.60       7.30      .50
          10         .65      1.20      3.1       5.70       8.30      .60

          12         .80      1.45      4.1       6.90      11.35      .65
          14         .95      2.30      5.0       7.90      13.90      .80
          16        1.25      2.95      6.6       9.20      18.15      .95
          18        1.40      3.70      8.6      10.40      22.80      1.10
          20        1.75      4.65      9.4      12.40      26.95      1.25

          24        2.20      5.90     13.3      15.50      33.60      1.50

      Handle  Pipe  Units:  Man hours include  handling, unloading,  hauling to  storage  and  erec-
         tion  site  and setting  and  aligning.
                                                                         #
      Cutting  Pipe  Units:  Man hours  include cutting  pipe  and  lining.  Lining  to  be  cut  square
         and flush  with  ends.

      Butt  Weld  Units:  Man hours include  making  complete electric  weld.  Cement lining  should
         be  wet with water  around  welding area.
      Sleeve  Joint  Units:  Man hours  include  slipping  on  of  sleeve,  aligning  and  welding  at
         both  ends.
      90°  Welded  Nozzle  Units:  Man hours  include  complete  operations  for  welding nozzle.

      Smooth  on  Cement  Units:  Man hours  include mixing  and patching weld joints  with cement.
      Man  hours  do  not  include  excavation  or  racks  or  supports.  See  respective  tables  for
      these  charges.