Page 155 - Estimators Piping Man Hour Manual
P. 155

138   Section Two-FIELD  FABRICATION







                            MAN  HOURS PER  UNITS  LISTED
           Size          Pipe        Cut  & Thread  Make-On s      BolM
          Inches        Per  L.F.       Each          Each           Eac

           1              .20            .10           .20           .50
           1-1/4          .22            .15           .30           .60
           1-1/2          .23            .16           .35           .65
           2              .25            .25           .40           .70
           2-1/2          .27                                        .80

           3              .30            --             --           .85
           4              .35            --            -            1.20
           6              .40            --            --           1.50
           8              .52            -             ..           2.10

      Pipe  Units:  Pipe  units  include  rigging,  erecting  and  aligning  of  pipe.  Pipe  is  normally
          furnished  in  10-foot lengths,  with ends  threaded  and  flanges  installed  at  the  factory.
          If  this  is  the  case,  add  15 percent  to  above pipe  man hours  for handling  additional
          weight.

      Make-On  Units:  Make-on  units  include  making  on  of  screwed  type  fittings.  Ells  - two
          make-ons,  tees  = three make-ons,  etc.
      Bolt-Up  Units: Bolt-up units include bolting together of flanged connections.
      All  Units:  All units  include unloading, handling and hauling to  storage and  erection  site.
      Man  hours do not include  supports  or scaffolding.  See respective  tables  for these  charges.