Section Two-FIELD  FABRICATION    135

                               ACCESS HOLES


                                  Carbon Steel Material

                                NET MAN HOURS EACH
        Nominal                         WALL THICKNESS
         Pipe                    OVER        OVER        OVER        OVER
          Size      UpTol"       I"to2"    2 "to  2- 1/2"  2-1/2" to 4"  4" to 6"

        2-1/2, 3, 4   1.8         2.0         „           --
         5,6,8        2.0         2.2         2.6         ..
         10,12        2.2         2.4         2.9         4.0         ~
        14, 16,  18   2.3         2.5         3.0         4.3         -

        20, 22, 24    2.5         2.9         3.1         4.5         6.8
        26, 28, 30    2.9         3.2         3.3         4.8         7.2
        32, 34, 36    3.1         3.3         3.7         5.1         7.6
        38, 40, 42    3.3         3.7         4.0         5.6         8,4
        44, 46, 48    3.7         4.0         4.4         6.7        10.1
         54,60        4.6         4.9         5.4         8.3        12.5
     Man hours include access holes through  1" diameter (drilled and tapped) for radiographic inspection of welds when
     specified or required.
     For openings larger than  1" in diameter, add 25% to the above man hours for each  V4" increase in  diameter.

     If plugs are to be included and seal welded, add 0.75 man hours each.