Section Two-FIELD  FABRICATION    137

                          PVC-PLASTIC          PIPE


                           MAN  HOURS PER  UNITS  LISTED
          Size       Handle Pipe  Cemented  Socket  Saddles    Handle  Valves
          Ins.        Per L.  F.    Joints  — Ea.    Each     PCV  Body - Ea,

          1/2            .07           .20           .38            .13
          3/4            .07           .22           .39            .16
          1              .07           .25           .40            .17
          1-1/4          .08           .27           .43            .20
          1-1/2          .08           .29           .45            .25
          2              .09           .33           .50            .35
          2-1/2          .09           .38           .55            .58

          3              .10           .45           .63            .85
         4               .11           .55           .73           1.25
         6               .12           .70           .90           1.60
         8               .14           .80          1.00           1.95
          10             .17          1.00          1.20           2.50

          12             .20          1.25          1.40           3.00
     Handle  Pipe  Units:  Man hours  include  handling,  hauling  rigging  and  aligning  in place.
     Cement  Socket  Joint  Units:  Man hours  include  cut,  square,  ream,  fit-up  and  make joint.
     Saddle  Units:  Man hours  include  fit-up,  drill  hole  in  header  and  cement  saddle  to header.
     Maximum  hole  size  is  assumed  to  be  l'/2  inch.  For  larger  branch  lines  the use  of tees
     should  be  estimated.  The  size  of  the  header  not  the  size  of  the  saddle  determines  the
     man hours that  apply.
     Handle  Valve  Units: Man hours  include  handling,  hauling  and  positioning  of  valve  only.
     Connections  of the type  as  required must be  added.
     Units  are for all wall thickness.
     Units  do not include  scaffolding.  See respective  table  for this  charge.
   149   150   151   152   153   154   155   156   157   158   159